[EventId:202403151220_confirmed] Prices for interval 15-Mar-2024 12:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 15 March 2024
PRICES ARE NOW CONFIRMED for trading interval 15-Mar-2024 12:20.
In accordance with Market Notice 115634 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202403151215_confirmed] Prices for interval 15-Mar-2024 12:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 15 March 2024
PRICES ARE NOW CONFIRMED for trading interval 15-Mar-2024 12:15.
In accordance with Market Notice 115633 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202403151205_confirmed] Prices for interval 15-Mar-2024 12:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 15 March 2024
PRICES ARE NOW CONFIRMED for trading interval 15-Mar-2024 12:05.
In accordance with Market Notice 115631 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Non-credible contingency event - SA region - 14/03/2024
Non-credible contingency event - SA region - 14/03/2024
At 2307 hrs the Tungkillo - Robertstown No. 1 275 kV Line and the Tungkillo East 275 kV Bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 12/03/2024
Non-credible contingency event - QLD region - 12/03/2024
At 0249 hrs the Strathmore - Clare South No 7208 132KV Line opened at Strathmore end only.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the SA region - 11/03/2024
Cancellation of Actual (LOR1) condition in the SA region - 11/03/2024
The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.115593 is cancelled at 1945 hrs 11/03/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 11/03/2024
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 11/03/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1830 hrs.
The Actual LOR1 condition is forecast to exist until 2030 hrs
The capacity reserve requirement is 498 MW
The minimum capacity reserve available is 255 MW
Manager NEM Real Time Operations
[EventId:202403102110_confirmed] Prices for interval 10-Mar-2024 21:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 2130 hrs on 10 March 2024
PRICES ARE NOW CONFIRMED for trading interval 10-Mar-2024 21:10.
In accordance with Market Notice 115576 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202403102130_confirmed] Prices for interval 10-Mar-2024 21:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 2130 hrs on 10 March 2024
PRICES ARE NOW CONFIRMED for trading interval 10-Mar-2024 21:30.
In accordance with Market Notice 115580 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.