Market Notices

116119PRICES UNCHANGED14/04/2024 09:14:28 AM

[EventId:202404140850_confirmed] Prices for interval 14-Apr-2024 08:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0910 hrs on 14 April 2024

PRICES ARE NOW CONFIRMED for trading interval 14-Apr-2024 08:50.

In accordance with Market Notice 116109 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
116118PRICES UNCHANGED14/04/2024 09:13:29 AM

[EventId:202404140910_confirmed] Prices for interval 14-Apr-2024 09:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0910 hrs on 14 April 2024

PRICES ARE NOW CONFIRMED for trading interval 14-Apr-2024 09:10.

In accordance with Market Notice 116113 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
116117PRICES UNCHANGED14/04/2024 09:12:31 AM

[EventId:202404140905_confirmed] Prices for interval 14-Apr-2024 09:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0910 hrs on 14 April 2024

PRICES ARE NOW CONFIRMED for trading interval 14-Apr-2024 09:05.

In accordance with Market Notice 116112 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
116116PRICES UNCHANGED14/04/2024 09:11:29 AM

[EventId:202404140900_confirmed] Prices for interval 14-Apr-2024 09:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0910 hrs on 14 April 2024

PRICES ARE NOW CONFIRMED for trading interval 14-Apr-2024 09:00.

In accordance with Market Notice 116111 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
116115PRICES UNCHANGED14/04/2024 09:10:22 AM

[EventId:202404140855_confirmed] Prices for interval 14-Apr-2024 08:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0910 hrs on 14 April 2024

PRICES ARE NOW CONFIRMED for trading interval 14-Apr-2024 08:55.

In accordance with Market Notice 116110 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
116114PRICES UNCHANGED14/04/2024 09:15:30 AM

[EventId:202404140845_confirmed] Prices for interval 14-Apr-2024 08:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0910 hrs on 14 April 2024

PRICES ARE NOW CONFIRMED for trading interval 14-Apr-2024 08:45.

In accordance with Market Notice 116108 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
116098POWER SYSTEM EVENTS12/04/2024 01:39:23 PM

Update - Non-credible contingency event - TAS region - 12/04/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 12/04/2024

Refer AEMO Electricity Market Notice 116095

At 1304 hrs the Sheffield - Farrell No.2 220 kV line was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
116095POWER SYSTEM EVENTS12/04/2024 11:22:09 AM

Non-credible contingency event - TAS region - 12/04/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 12/04/2024

At 1048 hrs the Sheffield - Farrell No.2 220 kV line tripped during restoration due to fault on the line.

AEMO did not instruct load shedding.

AEMO has been advised of disconnection of major industrial load approximately 550 MW.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
116078POWER SYSTEM EVENTS10/04/2024 03:44:19 PM

Update - Non-credible contingency event - QLD region - 10/04/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - QLD region - 10/04/2024

Refer AEMO Electricity Market Notice 116072

At 1540 hrs the Ingham South to Cardwell 132 kV line was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm