Filter by category
Filter by Date
Network Augmentation Commissioned - VIC Region - 27/08/2024
Network Augmentation Commissioned - VIC Region - 27/08/2024
Cressy - Golden Plains No. 1 220 kV Line has been commissioned.
Golden Plains Terminal Station has been commissioned.
Manager NEM Real Time Operations
CHG0095127 | Completed | Pre-Production | Pre-Prod NEM Reform - RMI (Retail Market Improvements) MSATS and eMDM Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod NEM Reform - RMI (Retail Market Improvements) MSATS and eMDM Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0096175 | Production | EMMS Production Bay transfer
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: EMMS Production Bay transfer
Change Start Date & Time: 02/09/2024 09:00:00 AEST
Change End Date & Time: 04/09/2024 16:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: EMMS Bay transfer is scheduled for 3rd September is not expected to have any impact. If any issues are identified because of this maintenance activity, please contact the AEMO Support Hub 1300 236 600.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities.
CHG0095221 | Cancelled | Production | A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Gas Hub
Change Title: A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
CHG0091459 | Cancelled | Production | MSATS CATS & URM Site Transfer BNE to NOR Data Centre
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS CATS & URM Site Transfer BNE to NOR Data Centre
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
Update - Non-credible contingency event - TAS region - 25/08/2024
Update - Non-credible contingency event - TAS region - 25/08/2024
Refer AEMO Electricity Market Notice 117782
At 1023 hrs the New Norfolk A 110kV Bus was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - TAS region - 25/08/2024
Non-credible contingency event - TAS region - 25/08/2024
At 0850 hrs the New Norfolk A 110kV Bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
CHG0095127 | Pre-Production | Pre-Prod NEM Reform - RMI (Retail Market Improvements) MSATS and eMDM Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod NEM Reform - RMI (Retail Market Improvements) MSATS and eMDM Release
Change Start Date & Time: 27/08/2024 13:00:00 AEST
Change End Date & Time: 27/08/2024 17:00:00 AEST
Outage Start Date & Time: 27/08/2024 13:00:00 AEST
Outage End Date & Time: 27/08/2024 17:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities.
CHG0095739 | Cancelled | Production | AEMO will be undertaking maintenance activities on the system.
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the system.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600