Filter by category
Filter by Date
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 120321
Direction is cancelled from: 1630 hrs 13/11/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer to Market Notice 120321
Direction is cancelled from: 1800 hrs 13/11/2024
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 14/11/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 120321
The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1800 hrs 13/11/2024.
The direction update is issued at 0830 hrs 13/11/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 120321
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1630 hrs 13/11/2024.
The direction update is issued at 0830 hrs 13/11/2024.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 13 November 2024
NON-CONFORMANCE QLD1 Region Wednesday, 13 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 13/11/2024 02:10 to 13/11/2024 02:50
Amount: 39 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Tuesday, 12 November 2024
NON-CONFORMANCE VIC1 Region Tuesday, 12 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YWPS2
Duration: 12/11/2024 19:10 to 12/11/2024 19:20
Amount: -23 MW
Constraint: NC-V_YWPS2
Auto-generated on behalf of Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 120321
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1700 hrs 12/11/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0730 hrs 13/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1700 hrs 13/11/2024 / further notice.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer to Market Notice 120321
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1700 hrs 12/11/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0130 hrs 13/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1630 hrs 13/11/2024 / further notice.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations