Market Notices

117394MARKET INTERVENTION21/07/2024 07:25:25 AM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0100 hrs 22/07/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
117393MARKET INTERVENTION20/07/2024 05:42:42 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Market Notice 117383

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 21/07/2024.

The direction update is issued at 1745 hrs 20/07/2024.

Manager NEM Real Time Operations
117388SETTLEMENTS RESIDUE20/07/2024 02:30:21 PM

[EventId:202407201430_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 20 July 2024 14:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1430 hrs on 20 July 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 20 July 2024.

Refer to market notice: 117382

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.

The negative residue constraint NRM_VIC1_NSW1 ceased operating at 1430 hrs on 20 July 2024.

This is an AEMO autogenerated Market Notice.
117386MARKET INTERVENTION20/07/2024 02:07:05 PM

Direction - SA region 20/07/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 20/07/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1405 hrs on 20/07/2024.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
117385MARKET INTERVENTION20/07/2024 01:53:30 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Market Notice 117370

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1500 hrs 20/07/2024.

The direction update is issued at 1350 hrs 20/07/2024.

Manager NEM Real Time Operations
117384MARKET INTERVENTION20/07/2024 02:04:23 PM

Direction - SA region 20/07/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 20/07/2024

Refer to Market Notice 117380


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1400 hrs 20/07/2024
Type of resource: generating unit
Required actions: remain synchronised and follow dispatch targets at 0030 hrs 21/07/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1500 hrs 21/07/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
117383MARKET INTERVENTION20/07/2024 02:02:41 PM

Direction - SA region 20/07/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 20/07/2024

Refer to Market Notice 117380


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1400 hrs 20/07/2024
Type of resource: generating unit
Required actions: remain synchronised and follow dispatch targets at 0030 hrs 21/07/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 22/07/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
117382SETTLEMENTS RESIDUE20/07/2024 01:30:31 PM

[EventId:202407201330_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 20 July 2024 13:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 20 July 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 20 July 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.

The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 1330 hrs on 20 July 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
117380MARKET INTERVENTION20/07/2024 01:28:26 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 117376

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0030 hrs 21/07/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1400 hrs 20/07/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm