115418MARKET INTERVENTION01/03/2024 03:36:33 PM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 29/02/2024

Refer Market Notice 115364

The AEMO Intervention Event and all associated directions are cancelled from 1535 hrs 01/03/2024

Manager NEM Real Time Operations
115414MARKET INTERVENTION01/03/2024 03:01:28 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 115403

The synchronous generating units currently expected to be synchronised in SA from 0100 hrs 02/03/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1700 hrs 01/03/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
115408INTER-REGIONAL TRANSFER01/03/2024 08:15:32 AM

Inter-regional transfer limit variation - Mt Piper 500/330 kV TIE1 Transformer - NSW region - 01/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Mt Piper 500/330 kV TIE1 Transformer - NSW region - 01/03/2024

At 0747 hrs 01/03/2024 there was an unplanned outage of Mt Piper 500/330 kV TIE1 Transformer.

Constraint set(s) invoked: N-MPTX

The following constraint set(s) invoked at 0755 hrs 01/03/2024
N-MPTX

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115403MARKET INTERVENTION01/03/2024 12:21:07 AM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0000 hrs 02/03/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations