Market Notices

117067RESERVE NOTICE19/06/2024 01:24:23 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

[1.] From 0800 hrs 20/06/2024 to 0830 hrs 20/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1358 MW.

[2.] From 1730 hrs 20/06/2024 to 1900 hrs 20/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1586 MW.


Manager NEM Real Time Operations
117066GENERAL NOTICE19/06/2024 12:14:34 PM

Planned outage of the Rowville - South Morang 500 kV line in the VIC region on 20/06/2024.

AEMO ELECTRICITY MARKET NOTICE

The Rowville - South Morang 500 kV line in the Victoria (VIC) region is planned to be out of service from 1400 hrs to 1630 hrs on 20/06/2024.

A credible contingency event during this planned outage could cause:
- A large reduction in generation in VIC; and/ or
- Restrict power transfer across the VIC - South Australia (SA) interconnector (Heywood interconnector).

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO Operations
117065RECLASSIFY CONTINGENCY19/06/2024 07:24:55 AM

Cancellation of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV

Cancellation time: 19/06/2024 07:24

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 117063

Auto-generated on behalf of Manager NEM Real Time Operations
117064RECLASSIFY CONTINGENCY19/06/2024 07:24:50 AM

Cancellation of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Cancellation time: 19/06/2024 07:24

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 117062

Auto-generated on behalf of Manager NEM Real Time Operations
117063RECLASSIFY CONTINGENCY19/06/2024 06:20:35 AM

Reclassification of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 19/06/2024 06:20 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
117062RECLASSIFY CONTINGENCY19/06/2024 06:20:36 AM

Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 19/06/2024 06:20 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
117060GENERAL NOTICE18/06/2024 09:25:56 PM

QNI Minor testing (Qld to NSW) 19th June 2024

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 117027

There is an opportunity for testing QNI Minor for flows from Qld to NSW up to 1300 MW on Wednesday 19th June 2024 from 0700 to 1000hrs.

This test includes a trip and reclose of a line in northern NSW.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
117059RESERVE NOTICE18/06/2024 06:45:58 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117048 is cancelled at1845 hrs 18/06/2024

Manager NEM Real Time Operations
117055RESERVE NOTICE18/06/2024 04:20:33 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.117046 has been updated at 1615 hrs to the following:

[1.] From 1730 hrs 19/06/2024 to 1930 hrs 19/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1521 MW.

Manager NEM Real Time Operations