Market Notices

117044MARKET SYSTEMS18/06/2024 11:44:51 AM

CHG0089794 | Cancelled | Production | EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities

Change Number: CHG0089794

Notification issued to: Market Notice
Notification Type: Cancelled

Change Type: Normal
Service/ Component: Electricity Market Management System

Change Title: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
117037MARKET SYSTEMS18/06/2024 08:21:17 AM

CHG0090550 | Cancelled | Production | Maintenance activities to be performed on the Gas Short Term Trading Market Systems Production.

Change Number: CHG0090550
Notification issued to: Market Notice

Notification Type: Cancelled
Change Type: Normal
Service/ Component: Gas FRC - CATS

Change Title: Maintenance activities to be performed on the Gas Short Term Trading Market Systems Production.

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
117033RESERVE NOTICE17/06/2024 09:51:45 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1730 hrs 18/06/2024 to 2030 hrs 18/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1148 MW.

Manager NEM Real Time Operations
117032RESERVE NOTICE17/06/2024 03:28:09 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 21/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 0000 hrs to 0030 hrs 21/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1677 MW.

AEMO Operations
117031RESERVE NOTICE17/06/2024 03:29:14 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117025 has been updated at 1400 hrs 17/06/2024 to the following:

1. From 0000 hrs to 0100 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1669 MW.

2. From 0600 hrs to 1000 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1651 MW.

3. From 1600 hrs to 2359 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1641 MW.

AEMO Operations
117030RESERVE NOTICE17/06/2024 03:27:16 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117024 has been updated at 1400 hrs 17/06/2024 to the following:

1. From 0600 hrs to 0900 hrs 19/06/2024.
The forecast capacity reserve requirement is 1692 MW.
The minimum capacity reserve available is 1565 MW.

2. From 1600 hrs to 2359 hrs 19/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1556 MW.

AEMO Operations
117029MARKET SYSTEMS17/06/2024 01:55:46 PM

CHG0089836 | Completed | Pre-Production | Renewal and update of AEMO's FBS-Test-Hub.aemo.com.au server certificate.

Change Number: CHG0089836
Notification issued to: Market Notice
Notification Type: Completed

Change Type: Normal
Service/Component: Gas Hub

Change Title: Renewal and update of AEMO's FBS-Test-Hub.aemo.com.au server certificate.

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
117027GENERAL NOTICE17/06/2024 10:59:14 AM

QNI Minor testing (Qld to NSW) 17th June 2024

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 114742

There is an opportunity for testing QNI Minor for flows from Qld to NSW up to 1300 MW on Monday 17th June 2024 from 1200 to 1800hrs.

This test includes a trip and reclose of a line in northern NSW.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
117025RESERVE NOTICE16/06/2024 02:44:09 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117019 has been updated at 1400 hrs 16/06/2024 to the following:

[2.] From 1600 hrs 19/06/2024 to 0030 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1535 MW.
.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm