Market Notices

115929SETTLEMENTS RESIDUE02/04/2024 01:10:22 PM

[EventId:202404021310_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 02 April 2024 13:10

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1310 hrs on 2 April 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 2 April 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1310 hrs on 2 April 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
115928MARKET INTERVENTION02/04/2024 01:05:46 PM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 02/04/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 02/04/2024

Refer Market Notice 115923

The AEMO Intervention Event and all associated directions are cancelled from 1305 hrs 02/04/2024

Manager NEM Real Time Operations
115923MARKET INTERVENTION02/04/2024 10:00:52 AM

Direction - SA region 02/04/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 02/04/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1005 hrs on 02/04/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
115920MARKET INTERVENTION02/04/2024 09:19:04 AM

Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA region

The synchronous generating units currently expected to be synchronised in SA from 0830 hrs 03/04/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1000 hrs 02/04/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
115911MARKET INTERVENTION01/04/2024 05:10:13 PM

Update - Direction - SA Region - 31/03/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 31/03/2024

Refer Market Notice 115905

The AEMO intervention event that commenced from interval ending 1705 hrs on 31/03/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
115905MARKET INTERVENTION31/03/2024 05:02:32 PM

Direction - SA region 31/03/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 31/03/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1705 hrs on 31/03/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
115902MARKET INTERVENTION31/03/2024 03:01:11 PM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 30/03/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 30/03/2024

Refer Market Notice 115895

The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs 31/03/2024

Manager NEM Real Time Operations
115898MARKET INTERVENTION31/03/2024 02:30:19 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 115897

The synchronous generating units currently expected to be synchronised in SA from 0800 hrs 01/04/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1700 hrs 31/03/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
115897MARKET INTERVENTION31/03/2024 11:51:05 AM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0800 hrs 01/04/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations