[EventId:202403031135_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 03 March 2024 11:35
Issued by Australian Energy Market Operator Ltd at 1135 hrs on 3 March 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 March 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1135 hrs on 3 March 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 29/12/2023
Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 29/12/2023
Refer AEMO Electricity Market Notice 115398.
Constraint set CA_BRIS_54F2D1C0 revoked 1710 hrs.
This constraint set contains equations with the following interconnector on the LHS;
VIC1-NSW1
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Para - Roseworthy 132 kV Line - SA region - 01/03/2024
Inter-regional transfer limit variation - Para - Roseworthy 132 kV Line - SA region - 01/03/2024
At 1515 hrs 01/03/2024 there was a short notice outage of Para - Roseworthy 132 kV Line.
The following constraint set was invoked at 1530 hrs 01/03/2024
S-PARS
This constraint set contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Mt Piper 500/330 kV TIE1 Transformer - NSW region - 01/03/2024
Inter-regional transfer limit variation - Mt Piper 500/330 kV TIE1 Transformer - NSW region - 01/03/2024
At 0747 hrs 01/03/2024 there was an unplanned outage of Mt Piper 500/330 kV TIE1 Transformer.
Constraint set(s) invoked: N-MPTX
The following constraint set(s) invoked at 0755 hrs 01/03/2024
N-MPTX
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations