Market Notices

115975POWER SYSTEM EVENTS05/04/2024 06:57:00 PM

Update - Non-credible contingency event - SA region - 25/03/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - SA region - 25/03/2024

Refer AEMO Electricity Market Notice 115794

At 1736 hrs Torrens Island BC3 275 kV CB was returned to service.
Torrens Island BW3 275 kV CB and Torrens Island - Lefevre 275 kV line previously returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
115948POWER SYSTEM EVENTS03/04/2024 11:45:55 PM

Non-credible contingency event - QLD region - 03/04/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 03/04/2024

At 2322 hrs the Kareeya PS units 1, 2, 3 and 4 tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.


The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
115947POWER SYSTEM EVENTS03/04/2024 11:16:35 PM

Update - Non-credible contingency event - NSW region - 03/04/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - NSW region - 03/04/2024

Refer AEMO Electricity Market Notice 115944

At 2301 hrs the Eraring Power Station Unit 1 and Unit 2 were returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
115944POWER SYSTEM EVENTS03/04/2024 02:21:43 PM

Non-credible contingency event - NSW region - 03/04/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 03/04/2024

At 1322 hrs the Eraring Power Station Unit 1 and the Eraring Power Station Unit 2 tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
115919INTER-REGIONAL TRANSFER02/04/2024 07:43:53 AM

Inter-regional transfer limit variation - Pelican Point to Parafield Gardens West 275kV Line - SA region - 02/04/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Pelican Point to Parafield Gardens West 275kV Line - SA region - 02/04/2024

A planned outage of Pelican Point to Parafield Gardens West 275kV Line in the SA region was scheduled from 0730 hrs 02/04/2024 to 1530 hrs 02/04/2024.

The outage has been cancelled at 0718 hrs 02/04/2024

Constraint set(s) revoked: S-PGPP, S-PPPG_PELPT

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115841POWER SYSTEM EVENTS27/03/2024 07:45:22 PM

Non-credible contingency event - VIC region - 27/03/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 27/03/2024

At 1736 hrs the Terang to Mortlake South 220 kV line opened at the Terang end only.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
115833POWER SYSTEM EVENTS27/03/2024 03:48:18 PM

Non-credible contingency event - SA region - Torrens Island 27/03/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - SA region - Torrens Island 27/03/2024

At 1529 hrs there was an unplanned outage of the following elements:
Torrens Island A 275 kV West Bus
Torrens Island AC3 275 kV CB

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
115828INTER-REGIONAL TRANSFER27/03/2024 10:08:49 AM

Inter-Regional Transfer limit variation - Murraylink

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Murraylink

There has been an unplanned outage of Murraylink.

The following constraint set was invoked at 1005 hrs 27/03/2024

I-MURRAYLINK

The constraint set contains the following interconnector on the left hand side.

V-S-MNSP1,VIC1-NSW1

Refer to AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
115794POWER SYSTEM EVENTS25/03/2024 03:48:06 PM

Non-credible contingency event - SA region - Torrens Island 25/03/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - SA region - Torrens Island 25/03/2024

At 1412 hrs there was an unplanned outage of the following elements:
Torrens Island BW3 275 kV CB
Torrens Island BC3 275 kV CB
Torrens Island - Lefevre 275 kV line

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations