Filter by category
Filter by Date
[EventId:202406111815_confirmed] Prices for interval 11-Jun-2024 18:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 11 June 2024
PRICES ARE NOW CONFIRMED for trading interval 11-Jun-2024 18:15.
In accordance with Market Notice 116956 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202406111810_confirmed] Prices for interval 11-Jun-2024 18:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 11 June 2024
PRICES ARE NOW CONFIRMED for trading interval 11-Jun-2024 18:10.
In accordance with Market Notice 116954 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202406111805_confirmed] Prices for interval 11-Jun-2024 18:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 11 June 2024
PRICES ARE NOW CONFIRMED for trading interval 11-Jun-2024 18:05.
In accordance with Market Notice 116953 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202406111800_confirmed] Prices for interval 11-Jun-2024 18:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 11 June 2024
PRICES ARE NOW CONFIRMED for trading interval 11-Jun-2024 18:00.
In accordance with Market Notice 116952 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202406111755_confirmed] Prices for interval 11-Jun-2024 17:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 11 June 2024
PRICES ARE NOW CONFIRMED for trading interval 11-Jun-2024 17:55.
In accordance with Market Notice 116951 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202406111750_confirmed] Prices for interval 11-Jun-2024 17:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 11 June 2024
PRICES ARE NOW CONFIRMED for trading interval 11-Jun-2024 17:50.
In accordance with Market Notice 116950 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Cancellation of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV
Cancellation time: 11/06/2024 17:36
Constraint set(s) revoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
Refer AEMO Electricity Market Notice 116947
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown
Cancellation time: 11/06/2024 17:36
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 116941
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV
Duration: 11/06/2024 16:24 until further notice
Constraint set(s) invoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
Auto-generated on behalf of Manager NEM Real Time Operations