Filter by category
Filter by Date
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 16/12/2024
The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 121795 has been updated at 1400 hrs 13/12/2024 to the following:
From 1630 hrs to 1730 hrs 16/12/2024.
The forecast capacity reserve requirement is 1120 MW.
The minimum capacity reserve available is 1031 MW.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121793 is cancelled at 1400 hrs 13/12/2024.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 17/12/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 121794 is cancelled at 1400 hrs 13/12/2024.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 16/12/2024
The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 121796 is cancelled at 1400 hrs 13/12/2024.
AEMO Operations
[EventId:202412131330_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 December 2024 13:30
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 13 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1330 hrs on 13 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Reclassification of a Non-Credible Contingency Event: Guybal Munjan - Chalumbin 857 275kV line line and Guybal Munjan - Chalumbin 858 275kV line line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Guybal Munjan - Chalumbin 857 275kV line and Guybal Munjan - Chalumbin 858 275kV line
Duration: 13/12/2024 13:14 until further notice
Constraint set(s) invoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Kamerunga to Barron Gorge No.7184 132 kV and the Kamerunga to Barron Gorge No.7143 132 kV lines in QLD due to lightning.
Reclassification of a non-credible contingency event as a credible contingency event due to lightning.
AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD
Lines: Kamerunga to Barron Gorge No.7184 132 kV and the Kamerunga to Barron Gorge No.7143 132 kV lines
Duration: 13/12/2024 13:07 until further notice
Constraint set(s) invoked: Nil
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV
Duration: 13/12/2024 12:51 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV
Duration: 13/12/2024 12:51 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations