121843RECLASSIFY CONTINGENCY13/12/2024 01:14:35 PM

Reclassification of a Non-Credible Contingency Event: Guybal Munjan - Chalumbin 857 275kV line line and Guybal Munjan - Chalumbin 858 275kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Guybal Munjan - Chalumbin 857 275kV line and Guybal Munjan - Chalumbin 858 275kV line

Duration: 13/12/2024 13:14 until further notice

Constraint set(s) invoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
121841RECLASSIFY CONTINGENCY13/12/2024 01:15:19 PM

Reclassification of a Non-Credible Contingency Event: Kamerunga to Barron Gorge No.7184 132 kV and the Kamerunga to Barron Gorge No.7143 132 kV lines in QLD due to lightning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to lightning.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD

Lines: Kamerunga to Barron Gorge No.7184 132 kV and the Kamerunga to Barron Gorge No.7143 132 kV lines
Duration: 13/12/2024 13:07 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
     
121838RECLASSIFY CONTINGENCY13/12/2024 12:51:12 PM

Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 13/12/2024 12:51 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
121837RECLASSIFY CONTINGENCY13/12/2024 12:51:13 PM

Reclassification of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 13/12/2024 12:51 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
121835RECLASSIFY CONTINGENCY13/12/2024 12:49:01 PM

Reclassification of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE

Duration: 13/12/2024 12:48 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
121832RECLASSIFY CONTINGENCY13/12/2024 12:42:39 PM

Reclassification of a Non-Credible Contingency Event: Collinsville North - Proserpine No.7125 132 kV line and Collinsville North - Proserpine No.7126 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Collinsville North - Proserpine No.7125 132 kV and Collinsville North - Proserpine No.7126 132 kV

Duration: 13/12/2024 12:42 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
121830SETTLEMENTS RESIDUE13/12/2024 12:30:31 PM

[EventId:202412131230_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 13 December 2024 12:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1230 hrs on 13 December 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 December 2024.

Refer to market notice: 121829

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1230 hrs on 13 December 2024.

This is an AEMO autogenerated Market Notice.
     
121829SETTLEMENTS RESIDUE13/12/2024 11:05:29 AM

[EventId:202412131105_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 December 2024 11:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1105 hrs on 13 December 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 December 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1105 hrs on 13 December 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
121826NON-CONFORMANCE13/12/2024 08:00:15 AM

NON-CONFORMANCE Region VIC1 Friday, 13 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Friday, 13 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BANN1
Duration: 13/12/2024 07:35 to 13/12/2024 08:00
Amount: 71 MW
Constraint: NC-V_BANN1

Auto-generated on behalf of Manager NEM Real Time Operations
     