118664RESERVE NOTICE07/10/2024 09:31:50 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118648 has been updated at 2130 hrs to the following:

[1.] From 1730 hrs 08/10/2024 to 1930 hrs 08/10/2024.
The forecast capacity reserve requirement is 1187 MW.
The minimum capacity reserve available is 863 MW.

Manager NEM Real Time Operations
     
118648RESERVE NOTICE07/10/2024 02:31:27 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118642 has been updated at 1430 hrs to the following:

[1.] From 1730 hrs 08/10/2024 to 1900 hrs 08/10/2024.
The forecast capacity reserve requirement is 1166 MW.
The minimum capacity reserve available is 1005 MW.

Manager NEM Real Time Operations
     
118642RESERVE NOTICE07/10/2024 01:15:46 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Periods:

[1.] From 1700 hrs 08/10/2024 to 1730 hrs 08/10/2024.
The forecast capacity reserve requirement is 1147 MW.
The minimum capacity reserve available is 904 MW.

[2.] From 1900 hrs 08/10/2024 to 2200 hrs 08/10/2024.
The forecast capacity reserve requirement is 1187 MW.
The minimum capacity reserve available is 731 MW.

Manager NEM Real Time Operations
     
118630RESERVE NOTICE06/10/2024 01:17:25 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118629 is cancelled at 1314 hrs 06/10/2024.

Manager NEM Real Time Operations
     
118629RESERVE NOTICE06/10/2024 12:56:44 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1730 hrs 07/10/2024 to 1930 hrs 07/10/2024.
The forecast capacity reserve requirement is 1108 MW.
The minimum capacity reserve available is 963 MW.

Manager NEM Real Time Operations
     
118596RESERVE NOTICE04/10/2024 02:52:16 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118562 has been updated at 1400 hrs 04/10/2024 to the following:

From 1730 hrs to 1930 hrs 08/10/2024.
The forecast capacity reserve requirement is 1097 MW.
The minimum capacity reserve available is 855 MW.

AEMO Operations
     
118562RESERVE NOTICE02/10/2024 03:38:42 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118548 has been updated at 1400 hrs 02/10/2024 to the following:

1. From 1730 hrs to 1930 hrs 08/10/2024.
The forecast capacity reserve requirement is 1107 MW.
The minimum capacity reserve available is 797 MW.

2. From 2100 hrs to 2130 hrs 08/10/2024.
The forecast capacity reserve requirement is 1118 MW.
The minimum capacity reserve available is 972 MW.

AEMO Operations
     
118548RESERVE NOTICE01/10/2024 03:10:01 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:

1. From 1730 hrs to 2030 hrs 08/10/2024.
The forecast capacity reserve requirement is 1108 MW.
The minimum capacity reserve available is 668 MW.

2. From 2100 hrs to 2200 hrs 08/10/2024.
The forecast capacity reserve requirement is 1120 MW.
The minimum capacity reserve available is 816 MW.

AEMO Operations
     
118528GENERAL NOTICE30/09/2024 09:20:28 AM

Heywood testing (SA to Vic) 30th September 2024

AEMO ELECTRICITY MARKET NOTICE

There is an opportunity for testing Heywood Interconnector (HIC) flow from South Australia to Victoria above 450MW and Victoria to South Australia above 450MW on 30th September from 9:00hrs to 17:00hrs

This test includes a trip and reclose of a line in South Australia.

Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Ben Blake
AEMO Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm