[EventId:202109291210_review] Prices for interval 29-Sep-2021 12:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1205 hrs on 29 September 2021
PRICES ARE SUBJECT TO REVIEW for dispatch interval 29-Sep-2021 12:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202109291205_review] Prices for interval 29-Sep-2021 12:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1200 hrs on 29 September 2021
PRICES ARE SUBJECT TO REVIEW for dispatch interval 29-Sep-2021 12:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202109291200_review] Prices for interval 29-Sep-2021 12:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1155 hrs on 29 September 2021
PRICES ARE SUBJECT TO REVIEW for dispatch interval 29-Sep-2021 12:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202109291155_review] Prices for interval 29-Sep-2021 11:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1150 hrs on 29 September 2021
PRICES ARE SUBJECT TO REVIEW for dispatch interval 29-Sep-2021 11:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202109291150_review] Prices for interval 29-Sep-2021 11:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1145 hrs on 29 September 2021
PRICES ARE SUBJECT TO REVIEW for dispatch interval 29-Sep-2021 11:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
CHG0070300 | Completed | Pre-Production | This outage is to allow the deployment of MSATS and eEMDM Pre-Production as part of 5MS Market Trials . MSATS will be unavailable during this outage period.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: This outage is to allow the deployment of MSATS and eEMDM Pre-Production as part of 5MS Market Trials . MSATS will be unavailable during this outage period.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0070166 | Completed | Pre-Production | Wholesale Demand Response (WDR)- Industry Test Release (Pre-Production).This outage is to allow the deployment of eMDM Pre-Production as part of WDR Industry Test.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Meter Data Management
Change Title: Wholesale Demand Response (WDR) - Industry Test Release (Pre-Production).This outage is to allow the deployment of eMDM Pre-Production as part of WDR Industry Test.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Update - Non-credible contingency event - NSW region - 28/09/2021
Update - Non-credible contingency event - NSW region - 28/09/2021
Refer AEMO ELECTRICITY MARKET NOTICE MN 91278
At 0854 hrs the Broken Hill - Silverton X6 220 kV Line and the Silverton 220kV/33kV Transformer was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Inter-regional transfer limit variation: Hazelwood - South Morang No 1 500 kV Line (VIC) - Voltage Control
The Hazelwood - South Morang No 1 500 kV Line has been de-energised to manage voltages in the Victoria region.
The following constraint set was invoked at 0120 hrs 29/09/2021.
V-HWSM
The constraint set contains equations with the following interconnectors on the LHS.
T-V-MNSP
V-S-MNSP1
V-SA
VIC1-NSW1
Refer to AEMO Network Outage Scheduler (NOS) for return to service details
Manager NEM Real Time Operations