Market Notices

118200RESERVE NOTICE08/09/2024 10:34:30 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

[1.] From 1830 hrs 10/09/2024 to 2030 hrs 10/09/2024.
The forecast capacity reserve requirement is 430 MW.
The minimum capacity reserve available is 403 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
118176RESERVE NOTICE07/09/2024 10:42:44 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118175 is cancelled at 2230 hrs 07/09/2024.

No LOR2 condition is currently forecast in the STPASA period.

Manager NEM Real Time Operations
     
118175RESERVE NOTICE07/09/2024 07:48:50 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/09/2024

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

[1.] From 1830 hrs 10/09/2024 to 1900 hrs 10/09/2024.
The forecast capacity reserve requirement is 415 MW.
The minimum capacity reserve available is 385 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
117565RESERVE NOTICE05/08/2024 09:47:16 PM

Cancellation of Actual (LOR1) condition in the SA region - 05/08/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the SA region - 05/08/2024

The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No. 117564 is cancelled at 2145 hrs 05/08/2024.

Manager NEM Real Time Operations
117564RESERVE NOTICE05/08/2024 09:25:40 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 05/08/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 05/08/2024

The actual LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 117563 has been updated at 2120 hrs to the following:

The Actual LOR1 condition is forecast to exist until 2130 hrs.

The forecast capacity reserve requirement is 450 MW.
The minimum capacity reserve available is 377 MW.

Manager NEM Real Time Operations
117563RESERVE NOTICE05/08/2024 08:44:48 PM

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 05/08/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 05/08/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 2030 hrs.
The Actual LOR1 condition is forecast to exist until 2100 hrs.

The capacity reserve requirement is 450 MW
The minimum capacity reserve available is 428 MW

Manager NEM Real Time Operations
117510RESERVE NOTICE30/07/2024 08:43:12 PM

Cancellation of Actual (LOR1) condition in the SA region - 30/07/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the SA region - 30/07/2024

The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No. 117509 is cancelled at 2040 hrs 30/07/2024.

Manager NEM Real Time Operations
117509RESERVE NOTICE30/07/2024 08:17:01 PM

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 30/07/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 30/07/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 2000 hrs.
The Actual LOR1 condition is forecast to exist until 2030 hrs

The capacity reserve requirement is 450 MW
The minimum capacity reserve available is 404 MW

Manager NEM Real Time Operations
117324LOAD RESTORE08/07/2024 09:58:40 PM

Cancellation - Load Restoration Direction in the NSW Region - 08/07/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Load Restoration Direction in the NSW Region - 08/07/2024

Refer to AEMO Electricity Market Notice 117322
Load restoration as directed is complete. Direction cancelled from 2200 hrs 08/07/2024

Manager NEM Real Time Operations