Market Notices

115478MARKET INTERVENTION04/03/2024 02:24:06 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 115474

The synchronous generating units currently expected to be synchronised in SA from 0000 hrs 05/03/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1500 hrs 04/03/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
115476SETTLEMENTS RESIDUE04/03/2024 11:30:20 AM

[EventId:202403041130_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 04 March 2024 11:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1130 hrs on 4 March 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 4 March 2024.

Refer to market notice: 115475

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1130 hrs on 4 March 2024.

This is an AEMO autogenerated Market Notice.
115475SETTLEMENTS RESIDUE04/03/2024 10:05:26 AM

[EventId:202403041005_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 04 March 2024 10:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1005 hrs on 4 March 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 4 March 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1005 hrs on 4 March 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
115474MARKET INTERVENTION04/03/2024 02:59:40 AM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0000 hrs 05/03/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
115460SETTLEMENTS RESIDUE03/03/2024 04:30:25 PM

[EventId:202403031630_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 03 March 2024 16:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1630 hrs on 3 March 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 March 2024.

Refer to market notice: 115457

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1630 hrs on 3 March 2024.

This is an AEMO autogenerated Market Notice.
115457SETTLEMENTS RESIDUE03/03/2024 03:35:20 PM

[EventId:202403031535_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 03 March 2024 15:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1535 hrs on 3 March 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 March 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1535 hrs on 3 March 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
115456MARKET INTERVENTION03/03/2024 05:46:29 PM

Update - Direction - SA Region - 02/03/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 02/03/2024

Refer Market Notice 115433

The AEMO intervention event that commenced from interval ending 1405 hrs on 02/03/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
115445SETTLEMENTS RESIDUE03/03/2024 01:30:18 PM

[EventId:202403031330_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 03 March 2024 13:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 3 March 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 March 2024.

Refer to market notice: 115443

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1330 hrs on 3 March 2024.

This is an AEMO autogenerated Market Notice.
115443SETTLEMENTS RESIDUE03/03/2024 11:35:25 AM

[EventId:202403031135_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 03 March 2024 11:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1135 hrs on 3 March 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 March 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1135 hrs on 3 March 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.