119258RECLASSIFY CONTINGENCY23/10/2024 06:41:37 PM

Reclassification of a Non-Credible Contingency Event: Gordon - Chapel St No 1 220kV line and Gordon - Chapel St No 2 220kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Gordon - Chapel St No 1 220kV and Gordon - Chapel St No 2 220kV

Duration: 23/10/2024 18:41 until further notice

Constraint set(s) invoked:
F-T-CSGO Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
T-CSGO_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
119248SETTLEMENTS RESIDUE23/10/2024 04:36:53 PM

[EventId:202410231635_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 23 October 2024 16:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1635 hrs on 23 October 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 23 October 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1635 hrs on 23 October 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
119229RESERVE NOTICE23/10/2024 03:05:00 PM

STPASA - Cancellation of the Forecast Lack of Reserve Level 1 (LOR1) in the NSW Region on 25/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119162 is cancelled at 1400 hrs 23/10/2024.

AEMO Operations
119213RESERVE NOTICE23/10/2024 01:02:06 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 24/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1730 hrs 24/10/2024 to 1930 hrs 24/10/2024.
The forecast capacity reserve requirement is 1187 MW.
The minimum capacity reserve available is 774 MW.

Manager NEM Real Time Operations
119211RESERVE NOTICE23/10/2024 01:03:39 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 24/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1800 hrs 24/10/2024 to 1930 hrs 24/10/2024.
The forecast capacity reserve requirement is 1420 MW.
The minimum capacity reserve available is 1306 MW.

Manager NEM Real Time Operations
119207MARKET SYSTEMS23/10/2024 10:25:05 AM

CHG0099235 | Production | Migrate Pre-Production (PPD) VLAN 108 Gateway in Norwest from the Old Core Switches to the New Core Switches.


Change Number: CHG0099235
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Local Area Network
Change Title: Migrate Pre-Production (PPD) VLAN 108 Gateway in Norwest from the Old Core Switches to the New Core Switches.
Change Start Date & Time: 24/10/2024 10:00:00 AEST
Change End Date & Time: 24/10/2024 16:00:00 AEST
Outage Start Date & Time: 24/10/2024 11:57:00 AEST
Outage End Date & Time: 24/10/2024 12:02:00 AEST
Environment: Production
Participant Impact and Requirements:
Planned maintenance has been scheduled for the 24th October, commencing 11:57am - 12:02pm AEST. During this time there will be a brief outage (Up to 30 seconds) impacting the following Pre-Production systems:

- MSATS Retail
- EMMS Wholesale
- GAS Market Systems
- WA Market Systems

The maintenance being carried out relates to infrastructure only, no application or functional changes are being performed. If you experience system related issues beyond the outage window (12:02pm) please contact the AEMO Support Hub.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .






119206MARKET SYSTEMS23/10/2024 10:21:46 AM

CHG0099241 | Production | Migrate DEV / TEST / Pre-Production (PPD) VLAN 104 Gateway in Norwest from the Old Core Switches to the New Core Switches.

Change Number: CHG0099241
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Local Area Network
Change Title: Migrate DEV / TEST / Pre-Production (PPD) VLAN 104 Gateway in Norwest from the Old Core Switches to the New Core Switches.
Change Start Date & Time: 24/10/2024 10:00:00 AEST
Change End Date & Time: 24/10/2024 16:00:00 AEST
Outage Start Date & Time: 24/10/2024 11:57:00 AEST
Outage End Date & Time: 24/10/2024 12:02:00 AEST
Environment: Production
Participant Impact and Requirements:
Planned maintenance has been scheduled for the 24th October, commencing 11:57am - 12:02pm AEST. During this time there will be a brief outage (Up to 30 seconds) impacting the following Pre-Production systems:

- MSATS Retail
- EMMS Wholesale
- GAS Market Systems
- WA Market Systems

The maintenance being carried out relates to infrastructure only, no application or functional changes are being performed. If you experience system related issues beyond the outage window (12:02pm) please contact the AEMO Support Hub.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .




119204SETTLEMENTS RESIDUE23/10/2024 08:15:25 AM

[EventId:202410230815_NRM_SA1_VIC1_stopped] NEGRES CONSTRAINT NRM_SA1_VIC1 ceased operating from 23 October 2024 08:15

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0815 hrs on 23 October 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 23 October 2024.

Refer to market notice: 119203

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the SA to VIC directional interconnector.

The negative residue constraint NRM_SA1_VIC1 ceased operating at 0815 hrs on 23 October 2024.

This is an AEMO autogenerated Market Notice.
119203SETTLEMENTS RESIDUE23/10/2024 07:35:28 AM

[EventId:202410230735_NRM_SA1_VIC1_started] NEGRES CONSTRAINT NRM_SA1_VIC1 started operating from 23 October 2024 07:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0735 hrs on 23 October 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 23 October 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the SA to VIC directional interconnector.

The negative residue constraint set NRM_SA1_VIC1 commenced operating from 0735 hrs on 23 October 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.