STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 24/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
From 1730 hrs to 1830 hrs 24/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1273 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120717 has been updated at 1400 hrs 21/11/2024 to the following:
1. From 1400 hrs to 1600 hrs 25/11/2024.
The forecast capacity reserve requirement is 1360 MW.
The minimum capacity reserve available is 680 MW.
2. From 1900 hrs to 2030 hrs 25/11/2024.
The forecast capacity reserve requirement is 1460 MW.
The minimum capacity reserve available is 730 MW.
AEMO Operations
Cancellation - AEMO Intervention Event - SA region 15/11/2024
Cancellation - AEMO Intervention Event - SA region 15/11/2024
Refer to Market Notice 120499
The AEMO Intervention Event and all associated directions are cancelled from 1335 hrs on 21/11/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 120723
Direction is cancelled from: 1330 hrs 21/11/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 120722
Direction is cancelled from: 1330 hrs 21/11/2024
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 21 November 2024
NON-CONFORMANCE NSW1 Region Thursday, 21 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 21/11/2024 01:55 to 21/11/2024 02:10
Amount: -20 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
Network Augmentation Commissioned - QLD Region - 21/11/2024
Network Augmentation Commissioned - QLD Region - 21/11/2024
Commissioned:
Belmont No.2 275 kV 150 MVar reactor
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 120680
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1500 hrs 21/11/2024.
The direction update is issued at 1630 hrs 20/11/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 120679
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1330 hrs 21/11/2024.
The direction update is issued at 1630 hrs 20/11/2024.
Manager NEM Real Time Operations