112936GENERAL NOTICE31/12/2023 10:47:14 AM

Minimum System Load 1 (MSL1) in the VIC Region on 31/12/2023

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1100 hrs 31/12/2023 to 1400 hrs 31/12/2023.
Minimum scheduled demand is forecast to be 1300 MW at 1300 hrs and the secure threshold for the forecast operating conditions is 2,000 MW.
AEMO is seeking a market response.
An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in action such as the direction of scheduled generation, curtailment of non-scheduled generation, and/or a direction to increase operational demand.

Manager NEM Real Time Operations
112893INTER-REGIONAL TRANSFER29/12/2023 05:27:51 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 29/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 29/12/2023

In order to maintain the power system in a secure operating state in the QLD region, AEMO has invoked automated constraint set CA_SYDS_549FBEF5 from 1650 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

N-Q-MNSP1

Manager NEM Real Time Operations
112860INTER-REGIONAL TRANSFER29/12/2023 04:03:53 AM

Inter-regional transfer limit variation - Para No.1 and No.2 275 kV SVC - SA region - 29/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation -Para No.1 and No.2 275 kV SVC - SA region - 29/12/2023

At 0355 hrs 29/12/2023 there was a short notice outage of Para No.1 and No.2 275 kV SVC.

The following constraint set(s) invoked at 0355 hrs 29/12/2023
S-X_PA_VC_2

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,V-S-MNSP1


Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112859INTER-REGIONAL TRANSFER29/12/2023 01:58:35 AM

Inter-regional transfer limit variation - Para No.1 275 kV SVC - SA region - 29/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation -Para No.1 275 kV SV - SA region - 29/12/2023

At 0145 hrs 29/12/2023 there was a short notice outage of Para No.1 275 kV SVC.

The following constraint set(s) invoked at 0145 hrs 29/12/2023
S-PA_VC1

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,V-S-MNSP1


Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112858INTER-REGIONAL TRANSFER28/12/2023 09:43:00 PM

Inter-regional transfer limit variation - Blyth West - Munno Para 275 kV line - SA region - 28/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Blyth West - Munno Para 275 kV line - SA region - 28/12/2023

At 2115 hrs 28/12/2023 there was an unplanned outage of the Blyth West - Munno Para 275 kV line.

The following constraint set(s) invoked at 2125 hrs 28/12/2023
S-BWMP

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112854INTER-REGIONAL TRANSFER28/12/2023 07:32:53 PM

Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 28/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 28/12/2023

At 1913 hrs 28/12/2023 there was an unplanned outage of the Hummocks - Waterloo 132 kV line.

The following constraint set(s) invoked at 1925 hrs 28/12/2023
S-HUWT

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112853INTER-REGIONAL TRANSFER28/12/2023 07:07:21 PM

Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 28/12/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 28/12/2023

Refer AEMO Electricity Market Notice 112852.

Constraint set CA_SYDS_549FBEF5 revoked 1850 hrs.

This constraint set contains equations with the following interconnector on the LHS;

N-Q-MNSP1


Manager NEM Real Time Operations
112852INTER-REGIONAL TRANSFER28/12/2023 06:44:09 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 28/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 28/12/2023

In order to maintain the power system in a secure operating state in the QLD region, AEMO has invoked automated constraint set CA_SYDS_549FBEF5 from 1830 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

N-Q-MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
112805GENERAL NOTICE27/12/2023 10:36:51 AM

NEM Local Temperature Alerts for QLD from 27 Dec 2023 to 31 Dec 2023

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

QLD
Dalby Ap (37+ Deg C): 29th Dec

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning