Market Notices

115675NON-CONFORMANCE17/03/2024 06:45:12 PM

NON-CONFORMANCE Region QLD1 Sunday, 17 March 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 17 March 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SWAN_E
Duration: 17/03/2024 18:40 to 17/03/2024 18:45
Amount: 59 MW
Constraint: NC-Q_SWAN_E

Auto-generated on behalf of Manager NEM Real Time Operations
115673NON-CONFORMANCE17/03/2024 06:00:14 PM

NON-CONFORMANCE Region QLD1 Sunday, 17 March 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 17 March 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SWAN_E
Duration: 17/03/2024 17:50 to 17/03/2024 18:00
Amount: -53 MW
Constraint: NC-Q_SWAN_E

Auto-generated on behalf of Manager NEM Real Time Operations
115656NON-CONFORMANCE16/03/2024 09:05:19 AM

NON-CONFORMANCE Region NSW1 Saturday, 16 March 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 16 March 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP6
Duration: 16/03/2024 09:00 to 16/03/2024 09:05
Amount: 15 MW
Constraint: NC-N_VP6

Auto-generated on behalf of Manager NEM Real Time Operations
115653NON-CONFORMANCE15/03/2024 03:40:17 PM

NON-CONFORMANCE Region QLD1 Friday, 15 March 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 15 March 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 15/03/2024 15:20 to 15/03/2024 15:40
Amount: -16 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
115624POWER SYSTEM EVENTS14/03/2024 11:47:59 PM

Non-credible contingency event - SA region - 14/03/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - SA region - 14/03/2024

At 2307 hrs the Tungkillo - Robertstown No. 1 275 kV Line and the Tungkillo East 275 kV Bus tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
115595POWER SYSTEM EVENTS12/03/2024 03:29:42 AM

Non-credible contingency event - QLD region - 12/03/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 12/03/2024

At 0249 hrs the Strathmore - Clare South No 7208 132KV Line opened at Strathmore end only.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
115594RESERVE NOTICE11/03/2024 07:52:57 PM

Cancellation of Actual (LOR1) condition in the SA region - 11/03/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the SA region - 11/03/2024

The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.115593 is cancelled at 1945 hrs 11/03/2024.

Manager NEM Real Time Operations
115593RESERVE NOTICE11/03/2024 06:42:56 PM

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 11/03/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 11/03/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1830 hrs.
The Actual LOR1 condition is forecast to exist until 2030 hrs

The capacity reserve requirement is 498 MW
The minimum capacity reserve available is 255 MW

Manager NEM Real Time Operations
115551NON-CONFORMANCE09/03/2024 02:20:20 PM

NON-CONFORMANCE Region NSW1 Saturday, 9 March 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 9 March 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: DPNTBG1, DPNTBL1
Aggregate Dispatch Group: DPNTBESS_ADG1
Duration: 09/03/2024 14:10 to 09/03/2024 14:20
Amount: 22 MW
Constraint: NC-N_DPNTBESS_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm