Filter by category
Filter by Date
NON-CONFORMANCE Region QLD1 Saturday, 2 March 2024
NON-CONFORMANCE QLD1 Region Saturday, 2 March 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: STAN-2
Duration: 02/03/2024 07:55 to 02/03/2024 08:05
Amount: 21 MW
Constraint: NC-Q_STAN-2
Auto-generated on behalf of Manager NEM Real Time Operations
Update - Lightning vulnerable equipment in QLD region
Update - Lightning vulnerable equipment in QLD region
Special Reclassification of Transmission Equipment during lightning
Refer to AEMO Electricity Market Notice 115270.
At 1029 hrs 28/02/2024 the Tully - Cardwell No.7389 132 kV Line tripped and auto reclosed and Ross - Woree No. 8905 275 kV Line tripped and auto reclosed.
The cause of the trip was identified as due to lightning.
In accordance with SO_OP_3715, AEMO now considers these lines to be vulnerable due to lightning.
Manager NEM Real Time Operations