118322POWER SYSTEM EVENTS19/09/2024 04:16:27 PM

Update - Non-credible contingency event - TAS region - 19/09/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 19/09/2024

Refer AEMO Electricity Market Notice 118321

At 1446 hrs the Gordon - Chapel St No 1 and No 2 220 kV lines were returned to service.

This non-credible contingency event was caused by lightning. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.


Manager NEM Real Time Operations
118321POWER SYSTEM EVENTS19/09/2024 03:28:41 PM

Update - Non-credible contingency event - TAS region - 19/09/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 19/09/2024

At 1340 hrs the Gordon - Chapel St No1 and No 2 220 kV lines tripped.

AEMO did not instruct load shedding.

AEMO has advised of approximately 112 MW disconnection of bulk electrical load,
disconnection of generation at Studland Bay Wind generator (71 MW) and 23 MW generation reduction at Gordon Power station.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
118320POWER SYSTEM EVENTS19/09/2024 01:54:59 PM

Non-credible contingency event - TAS region - 19/09/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 19/09/2024

At 1340 hrs the Gordon - Chapel St No1 and No 2 220 kV lines tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
118299RESERVE NOTICE16/09/2024 07:16:21 PM

Cancellation of Actual (LOR1) condition in the NSW region - 16/09/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 16/09/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.118298 is cancelled at 1915 hrs 16/09/2024.

Manager NEM Real Time Operations
118298RESERVE NOTICE16/09/2024 06:16:31 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/09/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/09/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 1274 MW

Manager NEM Real Time Operations
118277RESERVE NOTICE15/09/2024 11:28:16 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 118276 is cancelled at 1125 hrs 15/09/2024.

No LOR2 condition is currently forecast in the STPASA period.

Manager NEM Real Time Operations
118276RESERVE NOTICE14/09/2024 08:50:32 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17 Sep 2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period[s]:

[1.] From 1800 hrs 17/09/2024 to 1930 hrs 17/09/2024.
The forecast capacity reserve requirement is 1228 MW.
The minimum capacity reserve available is 1095 MW.


AEMO is seeking a market response.


Manager NEM Real Time Operations
118204RESERVE NOTICE09/09/2024 11:53:31 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118202 is cancelled at 1100 hrs 09/09/2024.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
118202RESERVE NOTICE09/09/2024 11:00:49 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 1830 hrs to 1930 hrs 10/09/2024.
The forecast capacity reserve requirement is 347 MW.
The minimum capacity reserve available is 343 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm