Market Notices

116899GENERAL NOTICE05/06/2024 12:11:55 PM

Network Augmentation Commissioned - QLD Region - 05/06/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - QLD Region - 05/06/2024

H20 Broadsound 275 kV Bus Reactor 1 (150 MVAr) has been commissioned as at 1043 hrs.

Manager NEM Real Time Operations
116882RESERVE NOTICE03/06/2024 05:49:43 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 04/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 116881 for the 04/06/2024 is cancelled at 1745 hrs 03/06/2024.

Manager NEM Real Time Operations
116881RESERVE NOTICE03/06/2024 05:20:08 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 04/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 1700 hrs 04/06/2024 to 1730 hrs 04/06/2024.
The forecast capacity reserve requirement is 448 MW.
The minimum capacity reserve available is 411 MW.

Manager NEM Real Time Operations
116879GENERAL NOTICE03/06/2024 10:49:16 AM

Fast Frequency Response Market - Increase in R1 and L1 FCAS dispatch caps from 11th June 2024

AEMO ELECTRICITY MARKET NOTICE

Following review of the operation of the Very Fast FCAS market, from 1300 hrs AEST on Tuesday 11th June AEMO will:

Increase the cap on dispatch of Very Fast Raise (R1) Contingency FCAS from 325 MW to 350 MW

Increase the cap on dispatch of Very Fast Lower (L1) Contingency FCAS from 200 MW to 225 MW

No other changes to the dispatch of Very Fast FCAS or FCAS constraint equation changes will be made on this date.

For information on the Fast Frequency Response (FFR) initiative please visit the website at: https://www.aemo.com.au/initiatives/major-programs/fast-frequency-response

Andrew Groom
AEMO Operations
116874GENERAL NOTICE01/06/2024 08:31:10 PM

Network Augmentation Commissioned - QLD Region - 01/06/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - QLD Region - 01/06/2024

H90 Tully South 275 kV Switching Station has been cut into the existing Ross - Woree No.8905 275 kV line to form the following circuits:

H13 Ross - H90 Tully South No.8905/1 275 kV line
H90 Tully South - H39 Woree No.8905/2 275 kV line

Manager NEM Real Time Operations
116869RESERVE NOTICE31/05/2024 02:40:42 PM

STPASA - Cancellation of the Forecast Lack of Reserve Level 1 (LOR1) in the NSW Region on 03/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116822 is cancelled at 1400 hrs 31/05/2024.

No LOR condition is currently forecast in the STPASA period.

AEMO Operations
116822RESERVE NOTICE27/05/2024 02:56:58 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 03/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1730 hrs to 1830 hrs 03/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1751 MW.

AEMO Operations
116737RESERVE NOTICE21/05/2024 03:29:47 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 23/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116724 is cancelled at 1400 hrs 21/05/2024.

No LOR condition is currently forecast in the STPASA period.

AEMO Operations
116736RESERVE NOTICE21/05/2024 03:30:30 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 22/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116723 is cancelled at 1400 hrs 21/05/2024.

No LOR condition is currently forecast in the STPASA period.

AEMO Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm