115593RESERVE NOTICE11/03/2024 06:42:56 PM

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 11/03/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 11/03/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1830 hrs.
The Actual LOR1 condition is forecast to exist until 2030 hrs

The capacity reserve requirement is 498 MW
The minimum capacity reserve available is 255 MW

Manager NEM Real Time Operations
115551NON-CONFORMANCE09/03/2024 02:20:20 PM

NON-CONFORMANCE Region NSW1 Saturday, 9 March 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 9 March 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: DPNTBG1, DPNTBL1
Aggregate Dispatch Group: DPNTBESS_ADG1
Duration: 09/03/2024 14:10 to 09/03/2024 14:20
Amount: 22 MW
Constraint: NC-N_DPNTBESS_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
115547INTER-REGIONAL TRANSFER08/03/2024 04:16:46 PM

Inter-regional transfer limit variation - South Pine SVC - QLD region - 08/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - South Pine SVC - QLD region - 08/03/2024

At 1605 hrs 08/03/2024 there was an unplanned outage of South Pine SVC.

The following constraint set(s) invoked at 1610 hrs 08/03/2024
Q-SP_VC

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115511INTER-REGIONAL TRANSFER06/03/2024 12:23:08 PM

Inter-regional transfer limit variation - Moorabool Sydenham No2 500 kV line - Vic region - 06/03/2024

AEMO ELECTRICITY MARKET NOTICE

At 1210 hrs 06/03/2024 in the Victoria region, the Moorabool Sydenham No2 500 kV line returned to service on temporary towers.

Constraint set changes.

Revoked:
V-MLSY_NOEMTT_R

This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1
V-SA
V-S-MNSP1
VIC1- NSW1

Refer Market Notices 114577, 114768, 114686, 114770 and 115120.

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115436NON-CONFORMANCE02/03/2024 01:55:18 PM

NON-CONFORMANCE Region VIC1 Saturday, 2 March 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Saturday, 2 March 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GLRWNSF1
Duration: 02/03/2024 13:45 to 02/03/2024 13:55
Amount: 110 MW
Constraint: NC-V_GLRWNSF1

Auto-generated on behalf of Manager NEM Real Time Operations
115429NON-CONFORMANCE02/03/2024 08:05:11 AM

NON-CONFORMANCE Region QLD1 Saturday, 2 March 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 2 March 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: STAN-2
Duration: 02/03/2024 07:55 to 02/03/2024 08:05
Amount: 21 MW
Constraint: NC-Q_STAN-2

Auto-generated on behalf of Manager NEM Real Time Operations
115424INTER-REGIONAL TRANSFER01/03/2024 05:37:17 PM

Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 29/12/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 29/12/2023

Refer AEMO Electricity Market Notice 115398.

Constraint set CA_BRIS_54F2D1C0 revoked 1710 hrs.

This constraint set contains equations with the following interconnector on the LHS;

VIC1-NSW1


Manager NEM Real Time Operations
115419INTER-REGIONAL TRANSFER01/03/2024 04:22:02 PM

Inter-regional transfer limit variation - Para - Roseworthy 132 kV Line - SA region - 01/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Para - Roseworthy 132 kV Line - SA region - 01/03/2024

At 1515 hrs 01/03/2024 there was a short notice outage of Para - Roseworthy 132 kV Line.

The following constraint set was invoked at 1530 hrs 01/03/2024
S-PARS

This constraint set contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115408INTER-REGIONAL TRANSFER01/03/2024 08:15:32 AM

Inter-regional transfer limit variation - Mt Piper 500/330 kV TIE1 Transformer - NSW region - 01/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Mt Piper 500/330 kV TIE1 Transformer - NSW region - 01/03/2024

At 0747 hrs 01/03/2024 there was an unplanned outage of Mt Piper 500/330 kV TIE1 Transformer.

Constraint set(s) invoked: N-MPTX

The following constraint set(s) invoked at 0755 hrs 01/03/2024
N-MPTX

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations