PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 29/07/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following Period:
[1.] From 0730 hrs 29/07/2024 to 0830 hrs 29/07/2024.
The forecast capacity reserve requirement is 557 MW.
The minimum capacity reserve available is 517 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 31/07/2024
The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117443 has been updated at 1400 hrs 27/07/2024 to the following:
From 0800 hrs 31/07/2024 to 0930 hrs 31/07/2024.
The forecast capacity reserve requirement is 557 MW.
The minimum capacity reserve available is 485 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 30/07/2024
The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117468 has been updated at 1400 hrs 27/07/2024 to the following:
From 0730 hrs 30/07/2024 to 0930 hrs 30/07/2024.
The forecast capacity reserve requirement is 557 MW.
The minimum capacity reserve available is 501 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 29/07/2024
The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117467 has been updated at 1400 hrs 27/07/2024 to the following:
[1.] From 0700 hrs 29/07/2024 to 0930 hrs 29/07/2024.
The forecast capacity reserve requirement is 557 MW.
The minimum capacity reserve available is 470 MW.
[2.] From 1730 hrs 29/07/2024 to 1930 hrs 29/07/2024.
The forecast capacity reserve requirement is 557 MW.
The minimum capacity reserve available is 534 MW.
AEMO Operations
CHG0091533 | Production | Planned Outage for the Gas Short Term Trading Market Systems Production.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Short Term Trading Market
Change Title: Planned Outage for the Gas Short Term Trading Market Systems Production.
Change Start Date & Time: 08/08/2024 09:00:00 AEST
Change End Date & Time: 08/08/2024 22:00:00 AEST
Outage Start Date & Time: 08/08/2024 18:30:00 AEST
Outage End Date & Time: 08/08/2024 21:00:00 AEST
Environment: Production
Participant Impact and Requirements: Gas Short Term Trading Market (STTM) services including SWEX and MIS, SPI and SBS will not be available during the outage window in Production.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 30/07/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:
From 0730 hrs to 0900 hrs 30/07/2024.
The forecast capacity reserve requirement is 555 MW.
The minimum capacity reserve available is 537 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 29/07/2024
The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117442 has been updated at 1400 hrs 26/07/2024 to the following:
From 0700 hrs to 0930 hrs 29/07/2024.
The forecast capacity reserve requirement is 555 MW.
The minimum capacity reserve available is 461 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 31/07/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:
From 0800 hrs to 0900 hrs 31/07/2024.
The forecast capacity reserve requirement is 555 MW.
The minimum capacity reserve available is 524 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 29/07/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:
From 0730 hrs to 0900 hrs 29/07/2024.
The forecast capacity reserve requirement is 555 MW.
The minimum capacity reserve available is 524 MW.
AEMO Operations