Market Notices

117055RESERVE NOTICE18/06/2024 04:20:33 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.117046 has been updated at 1615 hrs to the following:

[1.] From 1730 hrs 19/06/2024 to 1930 hrs 19/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1521 MW.

Manager NEM Real Time Operations
117052RESERVE NOTICE18/06/2024 04:01:53 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 22/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 0000 hrs to 0100 hrs 22/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1591 MW.

AEMO Operations
117051RESERVE NOTICE18/06/2024 04:00:55 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 21/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117032 has been updated at 1400 hrs 18/06/2024 to the following:

1. From 0030 hrs to 0130 hrs 21/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1422 MW.

2. From 0600 hrs to 1000 hrs 21/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1557 MW.

3. From 1600 hrs to 2359 hrs 21/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1543 MW.

AEMO Operations
117050RESERVE NOTICE18/06/2024 03:59:57 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117031 has been updated at 1400 hrs 18/06/2024 to the following:

1. From 0530 hrs to 0600 hrs 20/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1341 MW.

2. From 0900 hrs to 0930 hrs 20/06/2024.
The forecast capacity reserve requirement is 1652 MW.
The minimum capacity reserve available is 1236 MW.

3. From 1530 hrs to 1600 hrs 20/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1588 MW.

AEMO Operations
117048RESERVE NOTICE18/06/2024 02:47:53 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.117033 has been updated at 1500 hrs to the following:

[1.] From 1800 hrs 18/06/2024 to 1900 hrs 18/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1628 MW.


Manager NEM Real Time Operations
117047MARKET SYSTEMS18/06/2024 01:48:46 PM

CHG0090106 | Cancelled | Production | Identity Service Site Transfer

Change Number: CHG0090106

Notification issued to: Market Notice
Notification Type: Cancelled

Change Type: Normal
Service/ Component: Identity Service (IDS)

Change Title: Identity Service Site Transfer

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
117046RESERVE NOTICE18/06/2024 01:00:03 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Periods:

[1.] From 1700 hrs 19/06/2024 to 1730 hrs 19/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1385 MW.

[2.] From 1930 hrs 19/06/2024 to 2100 hrs 19/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1146 MW.

Manager NEM Real Time Operations
117044MARKET SYSTEMS18/06/2024 11:44:51 AM

CHG0089794 | Cancelled | Production | EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities

Change Number: CHG0089794

Notification issued to: Market Notice
Notification Type: Cancelled

Change Type: Normal
Service/ Component: Electricity Market Management System

Change Title: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
117037MARKET SYSTEMS18/06/2024 08:21:17 AM

CHG0090550 | Cancelled | Production | Maintenance activities to be performed on the Gas Short Term Trading Market Systems Production.

Change Number: CHG0090550
Notification issued to: Market Notice

Notification Type: Cancelled
Change Type: Normal
Service/ Component: Gas FRC - CATS

Change Title: Maintenance activities to be performed on the Gas Short Term Trading Market Systems Production.

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm