Market Notices

117007RESERVE NOTICE14/06/2024 03:46:12 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 21/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116980 is cancelled at 1400 hrs 14/06/2024.

AEMO Operations
117006RESERVE NOTICE14/06/2024 03:41:42 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116978 has been updated at 1400 hrs 14/06/2024 to the following:

1.From 0000 hrs to 0100 hrs 19/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1477 MW.

2. From 0530 hrs to 0930 hrs 19/06/2024.
The forecast capacity reserve requirement is 1715 MW.
The minimum capacity reserve available is 1186 MW.

3. From 1530 hrs to 2359 hrs 19/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1156 MW.

AEMO Operations
116999RESERVE NOTICE14/06/2024 03:42:59 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116977 has been updated at 1400 hrs 14/06/2024 to the following:

1. From 0630 hrs to 0830 hrs 18/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1412 MW.

2. From 1630 hrs to 2359 hrs 18/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1376 MW.

AEMO Operations
116997RESERVE NOTICE14/06/2024 03:40:43 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116976 is cancelled at 1400 hrs 14/06/2024.

AEMO Operations
116990RESERVE NOTICE14/06/2024 12:56:01 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1730 hrs 15/06/2024 to 1800 hrs 15/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1758 MW.

Manager NEM Real Time Operations
116984MARKET SYSTEMS13/06/2024 05:19:14 PM

CHG0089794 | Production | EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .

Change Number: CHG0089794

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal

Service/ Component: Electricity Market Management System
Change Title: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .

Change Start Date & Time: 17/06/2024 08:00:00 AEST
Change End Date & Time: 19/06/2024 17:30:00 AEST
Outage Start Date & Time: 18/06/2024 13:25:00 AEST
Outage End Date & Time: 18/06/2024 13:30:00 AEST

Environment: Production
Participant Impact and Requirements: The maintenance activity is not expected to have any impact however delays to Dispatch cycles, bid submission, and outage to the AEMO Markets Portal are possible during the outage window on Tuesday 18th June around 13:25 to 13:30 AEST.CDR will not be available during the outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
116983MARKET SYSTEMS13/06/2024 05:14:28 PM

CHG0090463 | Production | Planned Outage for the Gas Short Term Trading Market Systems Production.

Change Number: CHG0090463

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Short Term Trading Market
Change Title: Planned Outage for the Gas Short Term Trading Market Systems Production.

Change Start Date & Time: 19/06/2024 09:00:00 AEST
Change End Date & Time: 19/06/2024 22:00:00 AEST
Outage Start Date & Time: 19/06/2024 18:30:00 AEST
Outage End Date & Time: 19/06/2024 21:00:00 AEST

Environment: Production
Participant Impact and Requirements: Gas Short Term Trading Market (STTM) services including SWEX and MIS, SPI and SBS will not be available during the outage window in Production.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .

116982MARKET SYSTEMS13/06/2024 05:11:31 PM

CHG0090611 | Production | Changes to 7-day pre-dispatch (PD7DAY) reports to only publish 5 days.

Change Number: CHG0090611

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Dispatch

Change Title: Changes to 7-day pre-dispatch (PD7DAY) reports to only publish 5 days.
Change Start Date & Time: 17/06/2024 08:00:00 AEST
Change End Date & Time: 21/06/2024 17:30:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production

Participant Impact and Requirements: PD7DAY are reports published at least once a day and up to three times a day to assist with the administration of the gas industry's Gas Supply Guarantee and with short-term planning of gas supplies. AEMO has identified a performance issue with PD7DAY that has reduced the reliability of the delivery of the reports. As an interim measure, AEMO will reduce the outlook of PD7 DAY to 5 days which AEMO expects will reduce the frequency of missed reports.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
116981MARKET SYSTEMS13/06/2024 05:06:33 PM

CHG0090585 | Production | Dispatch Applications Upgrade

Change Number: CHG0090585

Notification issued to: Market Notice
Notification Type: Initial

Change Type: Normal
Service/ Component: EMMS - Dispatch
Change Title: Dispatch Applications Upgrade

Change Start Date & Time: 20/06/2024 09:00:00 AEST
Change End Date & Time: 21/06/2024 17:30:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production

Participant Impact and Requirements: Under this change, AEMO will upgrade the NEMDE solver used in Production for Dispatch, 5-Minute Predispatch, Predispatch and PD7 to a new version. AEMO will also upgrade other relevant applications for Dispatch ,5-Minute Predispatch ,Predispatch, PD7 as part of the Integrating Energy Storage Systems project (IESS).

No outage required.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm