121870NON-CONFORMANCE13/12/2024 04:55:23 PM

NON-CONFORMANCE Region QLD1 Friday, 13 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 13 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: KAREEYA1
Duration: 13/12/2024 16:50 to 13/12/2024 16:55
Amount: -21 MW
Constraint: NC-Q_KAREEYA1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121869RECLASSIFY CONTINGENCY13/12/2024 04:41:07 PM

Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Duration: 13/12/2024 16:41 until further notice

Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
     
121868RECLASSIFY CONTINGENCY13/12/2024 03:54:20 PM

Cancellation of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE

Cancellation time: 13/12/2024 15:54

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 121835

Auto-generated on behalf of Manager NEM Real Time Operations
     
121861PRICES SUBJECT TO REVIEW13/12/2024 03:38:49 PM

[EventId:202412131540_review] Prices for interval 13-Dec-2024 15:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1535 hrs on 13 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 13-Dec-2024 15:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121859PRICES SUBJECT TO REVIEW13/12/2024 03:34:40 PM

[EventId:202412131535_review] Prices for interval 13-Dec-2024 15:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1530 hrs on 13 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 13-Dec-2024 15:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121858RECLASSIFY CONTINGENCY13/12/2024 03:25:56 PM

Reclassification of a Non-Credible Contingency Event: Ross - Tully South - Woree No.8905 275 kV line line and Cardwell - Tully No.7389 132kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Ross - Tully South - Woree No.8905 275 kV line and Cardwell - Tully No.7389 132kV line

Duration: 13/12/2024 15:25 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
121857PRICES SUBJECT TO REVIEW13/12/2024 03:31:52 PM

[EventId:202412131530_review] Prices for interval 13-Dec-2024 15:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1525 hrs on 13 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 13-Dec-2024 15:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121855PRICES SUBJECT TO REVIEW13/12/2024 03:28:12 PM

[EventId:202412131525_review] Prices for interval 13-Dec-2024 15:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1520 hrs on 13 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 13-Dec-2024 15:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121854PRICES SUBJECT TO REVIEW13/12/2024 03:15:28 PM

[EventId:202412131520_review] Prices for interval 13-Dec-2024 15:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1515 hrs on 13 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 13-Dec-2024 15:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     