Reclassification of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE
Duration: 20/11/2024 13:46 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Collinsville North - Proserpine No.7125 132 kV line and Collinsville North - Proserpine No.7126 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Collinsville North - Proserpine No.7125 132 kV and Collinsville North - Proserpine No.7126 132 kV
Duration: 20/11/2024 12:18 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202411191800_confirmed] Prices for interval 19-Nov-2024 18:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1820 hrs on 19 November 2024
PRICES ARE NOW CONFIRMED for trading interval 19-Nov-2024 18:00.
In accordance with Market Notice 120685 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411191820_confirmed] Prices for interval 19-Nov-2024 18:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1820 hrs on 19 November 2024
PRICES ARE NOW CONFIRMED for trading interval 19-Nov-2024 18:20.
In accordance with Market Notice 120690 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411191815_confirmed] Prices for interval 19-Nov-2024 18:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1820 hrs on 19 November 2024
PRICES ARE NOW CONFIRMED for trading interval 19-Nov-2024 18:15.
In accordance with Market Notice 120689 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411191810_confirmed] Prices for interval 19-Nov-2024 18:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1820 hrs on 19 November 2024
PRICES ARE NOW CONFIRMED for trading interval 19-Nov-2024 18:10.
In accordance with Market Notice 120688 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411191805_confirmed] Prices for interval 19-Nov-2024 18:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1820 hrs on 19 November 2024
PRICES ARE NOW CONFIRMED for trading interval 19-Nov-2024 18:05.
In accordance with Market Notice 120686 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411191755_confirmed] Prices for interval 19-Nov-2024 17:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1820 hrs on 19 November 2024
PRICES ARE NOW CONFIRMED for trading interval 19-Nov-2024 17:55.
In accordance with Market Notice 120683 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Inter-regional transfer limit variation - Moorabool - Sydenham No. 2 500 kV Line - VIC region - 19/11/2024
Inter-regional transfer limit variation - Moorabool - Sydenham No. 2 500 kV Line - VIC region - 19/11/2024
A planned outage of Moorabool - Sydenham No. 2 500 kV Line in the VIC region was scheduled from 1130 hrs 13/11/2024 to 1900 hrs 20/11/2024.
The outage has been completed and Moorabool - Sydenham No. 2 500 kV Line returned to service at 1640 hrs 19/11/2024
Constraint set(s) revoked: V-MLSY_NOEMTT_R
Manager NEM Real Time Operations