NON-CONFORMANCE Region QLD1 Friday, 21 June 2024
NON-CONFORMANCE QLD1 Region Friday, 21 June 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 21/06/2024 11:25 to 21/06/2024 12:05
Amount: 39 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 20/06/2024
Cancellation of Actual (LOR1) condition in the NSW region - 20/06/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.117086 is cancelled at 1930hrs 20/06/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 20/06/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 20/06/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1726 MW
The minimum capacity reserve available is 1695 MW
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.117084 is cancelled at 1745 hrs 20/06/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.117080 has been updated at 1500 hrs to the following:
[1.] From 1730 hrs 20/06/2024 to 1900 hrs 20/06/2024.
The forecast capacity reserve requirement is 1770 MW.
The minimum capacity reserve available is 1682 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.117074 has been updated at 1239 hrs to the following:
[1.] From 1730 hrs 20/06/2024 to 1930 hrs 20/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1349 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117073 is cancelled at1845 hrs 19/06/2024
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.117067 has been updated at 1515 hrs to the following:
[1.] From 1730 hrs 20/06/2024 to 1900 hrs 20/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1541 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.117055 has been updated at 1515 hrs to the following:
[1.] From 1800 hrs 19/06/2024 to 1900 hrs 19/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1619 MW.
Manager NEM Real Time Operations