PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 10/03/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1830 hrs 10/03/2024 to 1900 hrs 10/03/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 575 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 10/03/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 115566 is cancelled at 1940 hrs 09/03/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 10/03/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1830 hrs 10/03/2024 to 1900 hrs 10/03/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 599 MW.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/03/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1800 hrs 14/03/2024 to 1830 hrs 14/03/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1493 MW.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - South Pine SVC - QLD region - 08/03/2024
Inter-regional transfer limit variation - South Pine SVC - QLD region - 08/03/2024
At 1605 hrs 08/03/2024 there was an unplanned outage of South Pine SVC.
The following constraint set(s) invoked at 1610 hrs 08/03/2024
Q-SP_VC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NEM Local Temperature Alerts for SA, TAS, VIC from 08 Mar 2024 to 12 Mar 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Adelaide West Terrace (39+ Deg C): 9th Mar, 10th Mar
Mt Gambier Ap (39+ Deg C): 9th Mar, 11th Mar
Port Augusta Ap (39+ Deg C): 8th Mar, 9th Mar, 10th Mar, 11th Mar, 12th Mar
TAS
Launceston Ti Tree Bend (33+ Deg C): 10th Mar
VIC
Latrobe Valley Ap (39+ Deg C): 9th Mar, 10th Mar, 11th Mar
Mildura Ap (39+ Deg C): 9th Mar, 10th Mar, 11th Mar, 12th Mar
Mortlake (39+ Deg C): 9th Mar, 11th Mar
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
NEM Local Temperature Alerts for SA, VIC from 07 Mar 2024 to 11 Mar 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Adelaide West Terrace (39+ Deg C): 9th Mar
Mt Gambier Ap (39+ Deg C): 9th Mar
Port Augusta Ap (39+ Deg C): 8th Mar, 9th Mar, 10th Mar, 11th Mar
VIC
Latrobe Valley Ap (39+ Deg C): 9th Mar, 10th Mar, 11th Mar
Mildura Ap (39+ Deg C): 9th Mar, 10th Mar, 11th Mar
Mortlake (39+ Deg C): 9th Mar
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Inter-regional transfer limit variation - Moorabool Sydenham No2 500 kV line - Vic region - 06/03/2024
At 1210 hrs 06/03/2024 in the Victoria region, the Moorabool Sydenham No2 500 kV line returned to service on temporary towers.
Constraint set changes.
Revoked:
V-MLSY_NOEMTT_R
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1
V-SA
V-S-MNSP1
VIC1- NSW1
Refer Market Notices 114577, 114768, 114686, 114770 and 115120.
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NEM Local Temperature Alerts for SA, VIC from 06 Mar 2024 to 10 Mar 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Adelaide West Terrace (39+ Deg C): 9th Mar, 10th Mar
Clare High School (39+ Deg C): 9th Mar
Mt Gambier Ap (39+ Deg C): 9th Mar
Port Augusta Ap (39+ Deg C): 8th Mar, 9th Mar, 10th Mar
VIC
Latrobe Valley Ap (39+ Deg C): 9th Mar, 10th Mar
Mildura Ap (39+ Deg C): 9th Mar, 10th Mar
Mortlake (39+ Deg C): 9th Mar
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts