Market Notices

116968MARKET SYSTEMS12/06/2024 09:22:54 AM

CHG0089854: Short Term Trading Market

Change Number: CHG0089854
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Short Term Trading Market
Change Title: Planned Outage for the Gas Short Term Trading Market Systems Production.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
116963SETTLEMENTS RESIDUE11/06/2024 07:00:26 PM

[EventId:202406111900_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 11 June 2024 19:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1900 hrs on 11 June 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 11 June 2024.

Refer to market notice: 116955

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1900 hrs on 11 June 2024.

This is an AEMO autogenerated Market Notice.
116955SETTLEMENTS RESIDUE11/06/2024 06:06:34 PM

[EventId:202406111805_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 11 June 2024 18:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1805 hrs on 11 June 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 11 June 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1805 hrs on 11 June 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
116940NON-CONFORMANCE11/06/2024 02:25:21 PM

NON-CONFORMANCE Region QLD1 Tuesday, 11 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 11 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 11/06/2024 12:45 to 11/06/2024 14:25
Amount: -23 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
116932NON-CONFORMANCE11/06/2024 12:05:16 PM

NON-CONFORMANCE Region QLD1 Tuesday, 11 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 11 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 11/06/2024 11:15 to 11/06/2024 12:05
Amount: -21 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
116930MARKET SYSTEMS11/06/2024 08:18:14 AM

CHG0089972 | Completed | Production | Planned Maintenance to Norwest Internet firewall.

Change Number: CHG0089972
Notification issued to: Market Notice Notification
Type: Completed
Change Type: Normal Service/Component: Internet Access
Change Title: Planned Maintenance to Norwest Internet firewall.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
116927NON-CONFORMANCE10/06/2024 11:40:17 PM

NON-CONFORMANCE Region QLD1 Monday, 10 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 10 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 10/06/2024 23:35 to 10/06/2024 23:40
Amount: 34 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
116922NON-CONFORMANCE10/06/2024 08:30:13 AM

NON-CONFORMANCE Region SA1 Monday, 10 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Monday, 10 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: CATHROCK
Duration: 10/06/2024 08:10 to 10/06/2024 08:30
Amount: 22 MW
Constraint: NC-S_CATHROCK

Auto-generated on behalf of Manager NEM Real Time Operations
116913NON-CONFORMANCE09/06/2024 08:55:15 AM

NON-CONFORMANCE Region NSW1 Sunday, 9 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Sunday, 9 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 09/06/2024 08:50 to 09/06/2024 08:55
Amount: 34 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm