117781INTER-REGIONAL TRANSFER25/08/2024 08:10:50 AM

Inter-regional transfer limit variation -Redcliffs No 2 220 kV Bus - VIC region - 25/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation -Redcliffs No 2 220 kV Bus - VIC region - 25/08/2024

A planned outage of Redcliffs No 2 220 kV Bus in the VIC region was scheduled from 0630 hrs 25/08/2024 to 1730 hrs 25/08/2024.

The outage has been cancelled at 0805 hrs.

The following constraint set(s) were invoked
Constraint Sets: V-KMRC, V-RCTS220CAPAUTO

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,T-V-MNSP1,V-SA,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
117759INTER-REGIONAL TRANSFER22/08/2024 10:54:09 PM

Inter-regional transfer limit variation - Dumaresq SVC - NSW region - 22/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Dumaresq SVC - NSW region - 22/08/2024

At 2238 hrs 22/08/2024 there was an unplanned of Dumaresq SVC

Constraint set(s) invoked: N-DM_SVC

The following constraint set(s) invoked at 2250 hrs 22/08/2024
N-DM_SVC

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
117737GENERAL NOTICE21/08/2024 10:37:27 AM

Planned outage of Kerang - Wemen 220 kV line in the VIC region on 23/08/2024.

AEMO ELECTRICITY MARKET NOTICE

The Kerang - Wemen 220 kV line in the Victorian (VIC) region is planned to be out of service from 0600 hrs to 1800 hrs on 23/08/2024.

A credible contingency event during this planned outage may require:
- Load shedding in the Victorian outer grid; and/ or
- Market intervention, such as the issuing of directions.

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO Operations
117725INTER-REGIONAL TRANSFER20/08/2024 09:28:20 AM

Inter-regional transfer limit variation - Kerang to Wemen 220kV line - VIC region - 20/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Kerang to Wemen 220kV line - VIC region - 20/08/2024

A planned outage of Kerang to Wemen 220kV line in the VIC region was scheduled from 0600 hrs 20/08/2024 to 1930 hrs 20/08/2024.

The outage has been completed and Kerang to Wemen 220kV line returned to service at 0925 hrs 20/08/2024

Constraint set revoked: V-KGWT

Manager NEM Real Time Operations
117724INTER-REGIONAL TRANSFER19/08/2024 09:54:20 PM

Inter-Regional Transfer limit variation - Murraylink

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Murraylink

There has been an unplanned outage of the Murraylink interconnector.

The following constraint set was invoked at 2155 hrs 19/08/2024

I-MURRAYLINK

The constraint set contains the following interconnector on the left hand side.

V-S-MNSP1,VIC1-NSW1

Refer to AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
117694GENERAL NOTICE16/08/2024 10:44:53 AM

Network Augmentation Commissioned - NSW Region - 16/08/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - NSW Region - 16/08/2024

Commissioned: Munmorah - Waratah S BESS 2Y 330 kV Line

Manager NEM Real Time Operations
117691GENERAL NOTICE15/08/2024 10:28:59 PM

Network Augmentation Commissioned - NSW Region - 15/08/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - NSW Region - 15/08/2024

Commissioned: Munmorah - Waratah S BESS 2W 330 kV Line

Manager NEM Real Time Operations
117677INTER-REGIONAL TRANSFER14/08/2024 04:22:12 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 1 Leg of Directlink .

The following constraint set was invoked at 1620 hrs 14/08/2024

N-MBTE_1

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
117672INTER-REGIONAL TRANSFER14/08/2024 11:08:17 AM

Inter-regional transfer limit variation - CollectorWF-Marulan 4 330kV LINE - NSW region - 14/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - CollectorWF-Marulan 4 330kV LINE - NSW region - 14/08/2024

At 1006 hrs 14/08/2024 there was a short notice outage of CollectorWF-Marulan 4 330kV LINE.

The following constraint set(s) invoked at 1000 hrs 14/08/2024
N-CTMN_4_WG_CLOSE

This constraint set(s) contains equations with the following interconnectors on the LHS.
VIC1-NSW1,N-Q-MNSP1,NSW1-QLD1,V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations