Filter by category
Filter by Date
[EventId:202408271005_confirmed] Prices for interval 27-Aug-2024 10:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1020 hrs on 27 August 2024
PRICES ARE NOW CONFIRMED for trading interval 27-Aug-2024 10:05.
In accordance with Market Notice 117821 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202408270955_confirmed] Prices for interval 27-Aug-2024 09:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1020 hrs on 27 August 2024
PRICES ARE NOW CONFIRMED for trading interval 27-Aug-2024 09:55.
In accordance with Market Notice 117819 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
CHG0095221 | Cancelled | Production | A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Gas Hub
Change Title: A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
CHG0091459 | Cancelled | Production | MSATS CATS & URM Site Transfer BNE to NOR Data Centre
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS CATS & URM Site Transfer BNE to NOR Data Centre
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
CHG0095127 | Pre-Production | Pre-Prod NEM Reform - RMI (Retail Market Improvements) MSATS and eMDM Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod NEM Reform - RMI (Retail Market Improvements) MSATS and eMDM Release
Change Start Date & Time: 27/08/2024 13:00:00 AEST
Change End Date & Time: 27/08/2024 17:00:00 AEST
Outage Start Date & Time: 27/08/2024 13:00:00 AEST
Outage End Date & Time: 27/08/2024 17:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities.
CHG0095739 | Cancelled | Production | AEMO will be undertaking maintenance activities on the system.
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the system.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
CHG0093465 | Completed | Production | AEMO will be undertaking maintenance activities on the STTM system.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the STTM system.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0095840 | Completed | Production | AEMO will be undertaking maintenance activities on the DWGM system
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the DWGM system
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0095840 | Production | AEMO will be undertaking maintenance activities on the DWGM system
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the DWGM system
Change Start Date & Time: 20/08/2024 18:30:35 AEST
Change End Date & Time: 21/08/2024 01:30:35 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements:
AEMO will be undertaking maintenance activities on the DWGM system. Whilst no outage is expected there is potential for transient performance degradation during the change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .