115841POWER SYSTEM EVENTS27/03/2024 07:45:22 PM

Non-credible contingency event - VIC region - 27/03/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 27/03/2024

At 1736 hrs the Terang to Mortlake South 220 kV line opened at the Terang end only.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
115833POWER SYSTEM EVENTS27/03/2024 03:48:18 PM

Non-credible contingency event - SA region - Torrens Island 27/03/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - SA region - Torrens Island 27/03/2024

At 1529 hrs there was an unplanned outage of the following elements:
Torrens Island A 275 kV West Bus
Torrens Island AC3 275 kV CB

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
115794POWER SYSTEM EVENTS25/03/2024 03:48:06 PM

Non-credible contingency event - SA region - Torrens Island 25/03/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - SA region - Torrens Island 25/03/2024

At 1412 hrs there was an unplanned outage of the following elements:
Torrens Island BW3 275 kV CB
Torrens Island BC3 275 kV CB
Torrens Island - Lefevre 275 kV line

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
115783POWER SYSTEM EVENTS25/03/2024 02:17:51 PM

Update - Non-credible contingency event - SA region - 25/03/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - SA region - 25/03/2024

Refer AEMO Electricity Market Notice 115777

At 1350 hrs the Davenport - Brinkworth 275 kV line, Brinkworth No 3 275/132 kV transformer
and Brinkworth - Templers West 275 kV line was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
115777POWER SYSTEM EVENTS25/03/2024 09:27:07 AM

Non-credible contingency event - SA region - 25/03/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - SA region - 25/03/2024

At 0810 hrs there was an unplanned outage of the following elemets:
Davenport - Brinkworth 275 kV line
Brinkworth No 3 275/132 kV transformer
Brinkworth - Templers West 275 kV line

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.


The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
115771POWER SYSTEM EVENTS24/03/2024 04:39:39 PM

Update - Non-credible contingency event - SA region - 14/03/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - SA region - 14/03/2024

Refer AEMO Electricity Market Notice 115624

At 1635 hrs the Tungkillo - Robertstown No. 1 275 kV Line and the Tungkillo East 275 kV Bus was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
115756PRICES SUBJECT TO REVIEW24/03/2024 12:15:24 PM

[EventId:202403241220_review] Prices for interval 24-Mar-2024 12:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1215 hrs on 24 March 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Mar-2024 12:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
115755PRICES SUBJECT TO REVIEW24/03/2024 12:10:11 PM

[EventId:202403241215_review] Prices for interval 24-Mar-2024 12:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1210 hrs on 24 March 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Mar-2024 12:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
115754PRICES SUBJECT TO REVIEW24/03/2024 12:05:21 PM

[EventId:202403241210_review] Prices for interval 24-Mar-2024 12:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1205 hrs on 24 March 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Mar-2024 12:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm