STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region beginning on 16/12/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period[s]:
[1.] From 1600 hrs 16/12/2024 to 2000 hrs 16/12/2024.
The forecast capacity reserve requirement is 1103 MW.
The minimum capacity reserve available is 710 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
[EventId:202412131515_confirmed] Prices for interval 13-Dec-2024 15:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1540 hrs on 13 December 2024
PRICES ARE NOW CONFIRMED for trading interval 13-Dec-2024 15:15.
In accordance with Market Notice 121853 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412131540_confirmed] Prices for interval 13-Dec-2024 15:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1540 hrs on 13 December 2024
PRICES ARE NOW CONFIRMED for trading interval 13-Dec-2024 15:40.
In accordance with Market Notice 121861 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412131535_confirmed] Prices for interval 13-Dec-2024 15:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1540 hrs on 13 December 2024
PRICES ARE NOW CONFIRMED for trading interval 13-Dec-2024 15:35.
In accordance with Market Notice 121859 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412131530_confirmed] Prices for interval 13-Dec-2024 15:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1540 hrs on 13 December 2024
PRICES ARE NOW CONFIRMED for trading interval 13-Dec-2024 15:30.
In accordance with Market Notice 121857 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412131525_confirmed] Prices for interval 13-Dec-2024 15:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1540 hrs on 13 December 2024
PRICES ARE NOW CONFIRMED for trading interval 13-Dec-2024 15:25.
In accordance with Market Notice 121855 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412131520_confirmed] Prices for interval 13-Dec-2024 15:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1540 hrs on 13 December 2024
PRICES ARE NOW CONFIRMED for trading interval 13-Dec-2024 15:20.
In accordance with Market Notice 121854 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412131510_confirmed] Prices for interval 13-Dec-2024 15:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1535 hrs on 13 December 2024
PRICES ARE NOW CONFIRMED for trading interval 13-Dec-2024 15:10.
In accordance with Market Notice 121852 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
CORRECTION: Update - Vulnerable lines in QLD region
Update - Lightning vulnerable lines in QLD region
Refer to AEMO Electricity Market Notice 121840
Fix typo: Line 7141 should read Line 7143
At 2026 hrs 12/12/2024 the Kamerunga to Barron Gorge 132 kV Line 7184 and the Kamerunga to Barron Gorge 132 kV Line 7143 tripped.
The cause of the trip was identified as due to lightning.
In accordance with SO_OP_3715, AEMO now considers the Kamerunga to Barron Gorge 132 kV Line 7184 and the Kamerunga to Barron Gorge 132 kV Line 7143 to be vulnerable with a category of probable due to lightning.
Manager NEM Real Time Operations