Market Notices

121262RESERVE NOTICE29/11/2024 05:43:53 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/11/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/11/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs

The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1301 MW

Manager NEM Real Time Operations
     
121261RESERVE NOTICE29/11/2024 05:23:02 PM

Cancellation of Actual (LOR1) condition in the NSW region - 29/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 29/11/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121260 is cancelled at 1717 hrs 29/11/2024.

Manager NEM Real Time Operations
     
121260RESERVE NOTICE29/11/2024 04:54:05 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/11/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/11/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1730 hrs

The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1183 MW

Manager NEM Real Time Operations
     
121169PRICE ADJUSTMENT28/11/2024 02:18:30 PM

[EventId:202411271510_confirmed] Prices for interval 27-Nov-2024 15:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1418 hrs on 28 November 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Nov-2024 15:10.

In accordance with Market Notice 121092 AEMO has reviewed this trading interval and determined that:
- Over-Constrained Dispatch has been resolved for this interval

Changed Prices ($/MWh)

TYPE
Region Original Adjusted
Price Price
ENERGY
VIC1 -$30.00 -$29.50
RAISE60SEC
NSW1 $0.10 $0.05
QLD1 $0.10 $0.05
SA1 $0.10 $0.05
VIC1 $0.10 $0.05


This is an AEMO autogenerated Market Notice.
     
121167MARKET INTERVENTION28/11/2024 03:01:25 PM

Cancellation - AEMO Intervention Event - SA region 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 27/11/2024

Refer to Market Notice 121094

The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs on 28/11/2024.


Manager NEM Real Time Operations
     
121166MARKET INTERVENTION28/11/2024 02:59:59 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 121091

Direction is cancelled from: 1500 hrs 28/11/2024

Manager NEM Real Time Operations
     
121165MARKET INTERVENTION28/11/2024 02:29:51 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 121090

Direction is cancelled from: 1430 hrs 28/11/2024

Manager NEM Real Time Operations
     
121147INTER-REGIONAL TRANSFER28/11/2024 12:32:16 PM

Cancellation - Inter-regional transfer limit variation - to manage Power System Security in NSW region - 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

Refer AEMO Electricity Market Notice 121142

Constraint set I-QN_1000 was invoked from 0955 hrs until 1230 hrs 28/11/2024.

This constraint set contains equations with the following interconnector on the LHS;

NSW1-QLD1

Manager NEM Real Time Operations
     
121142INTER-REGIONAL TRANSFER28/11/2024 10:02:47 AM

Inter-regional transfer limit variation - to manage Power System Security in NSW region - 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked the following constraint set I-QN_1000 from 0955 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

NSW1-QLD1

Manager NEM Real Time Operations
     
X