Filter by category
Filter by Date
[EventId:202412120140_confirmed] Prices for interval 12-Dec-2024 01:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0205 hrs on 12 December 2024
PRICES ARE NOW CONFIRMED for trading interval 12-Dec-2024 01:40.
In accordance with Market Notice 121740 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412120205_review] Prices for interval 12-Dec-2024 02:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 0200 hrs on 12 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 02:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412120200_review] Prices for interval 12-Dec-2024 02:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 0155 hrs on 12 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 02:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412120155_review] Prices for interval 12-Dec-2024 01:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 0150 hrs on 12 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 01:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412120150_review] Prices for interval 12-Dec-2024 01:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 0145 hrs on 12 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 01:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412120145_review] Prices for interval 12-Dec-2024 01:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 0140 hrs on 12 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 01:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412120140_review] Prices for interval 12-Dec-2024 01:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 0135 hrs on 12 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 01:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
CHG0100201 | Planned maintenance affecting the AEMO Market Network ***Outage Updated***
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MarketNet
Change Title: Planned maintenance affecting the AEMO Market Network ***Outage Updated***
Change Start Date & Time: 16/12/2024 08:00:00 AEST
Change End Date & Time: 17/12/2024 17:00:00 AEST
Outage 1 Start Date & Time: 16/12/2024 08:12:00 AEST
Outage 1 End Date & Time: 16/12/2024 08:13:00 AEST
Outage 2 Start Date & Time: 16/12/2024 15:12:00 AEST
Outage 2 End Date & Time: 16/12/2024 15:13:00 AEST
Environment: Production
Participant Impact and Requirements: Planned maintenance will be conducted on the 16th of December 2024, between 08:00AM and 05:00PM AEST on the core network infrastructure within the AEMO Market Network in Brisbane.
During the change, there will be two instances of 1-3 second service disruption to MarketNet Services accessed via Brisbane as traffic moves from the active to the standby load balancing unit. All Services should return to normal after this time. Traffic via Sydney will not be affected during this time. AEMO recommends that all market participants with site to site VPN connections currently connected via Brisbane, to switch these connections to the Sydney site as a precaution.
Participants connecting via IPWAN and/or SSL VPN will be automatically connected to the Sydney site and do not need to take any action.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0100220 | Completed | Pre-Production | Pre-Production Electricity Market Management System (EMMS) Maintenance - Outages
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Electricity Market Management System_PreProd
Change Title: Pre-Production Electricity Market Management System (EMMS) Maintenance - Outages
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.