121760RESERVE NOTICE12/12/2024 09:04:31 AM

STPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 121734 has been updated at 0800 hrs 12/12/2024 to the following:

From 1500 hrs to 1930 hrs 16/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 733 MW at 1730 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121759RECALL GEN CAPACITY12/12/2024 09:09:42 AM

Request for Generator Recall Information for the period 16/12/2024 and 17/12/2024 for Region NSW

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 121760, 121762, and 121765.

Please provide Generator Recall Information for the period from 16/12/2024 to 17/12/2024, by 1200 hrs on 13/12/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf


AEMO Operations
     
121757RECALL GEN CAPACITY12/12/2024 09:07:27 AM

Request for Generator Recall Information for the period 16/12/2024 for Region VIC

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 121767.

Please provide Generator Recall Information for the period 16/12/2024, by 1200 hrs on 13/12/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf


AEMO Operations
     
121755NON-CONFORMANCE12/12/2024 05:40:16 AM

NON-CONFORMANCE Region NSW1 Thursday, 12 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 12 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW02
Duration: 12/12/2024 05:35 to 12/12/2024 05:40
Amount: -31 MW
Constraint: NC-N_BW02

Auto-generated on behalf of Manager NEM Real Time Operations
     
121734RESERVE NOTICE12/12/2024 12:42:05 AM

STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

[1.] From 1530 hrs 16/12/2024 to 1600 hrs 16/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 10 MW at 1530 hrs.

[2.] From 1700 hrs 16/12/2024 to 1830 hrs 16/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 106 MW at 1730 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
121707NON-CONFORMANCE11/12/2024 02:20:15 AM

NON-CONFORMANCE Region QLD1 Wednesday, 11 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 11 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 11/12/2024 02:00 to 11/12/2024 02:20
Amount: -10 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
121703NON-CONFORMANCE10/12/2024 06:25:21 PM

NON-CONFORMANCE Region QLD1 Tuesday, 10 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 10 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 10/12/2024 17:55 to 10/12/2024 18:25
Amount: -18 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121684NON-CONFORMANCE10/12/2024 01:00:18 AM

NON-CONFORMANCE Region QLD1 Tuesday, 10 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 10 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 10/12/2024 00:55 to 10/12/2024 01:00
Amount: -13 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
121652NON-CONFORMANCE09/12/2024 11:15:15 AM

NON-CONFORMANCE Region QLD1 Monday, 9 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 9 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MIDDLSF1
Duration: 09/12/2024 10:25 to 09/12/2024 11:15
Amount: 22 MW
Constraint: NC-Q_MIDDLSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     