Filter by category
Filter by Date
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/11/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/11/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs
The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1301 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 29/11/2024
Cancellation of Actual (LOR1) condition in the NSW region - 29/11/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121260 is cancelled at 1717 hrs 29/11/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/11/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/11/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1730 hrs
The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1183 MW
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 27/11/2024
Cancellation - AEMO Intervention Event - SA region 27/11/2024
Refer to Market Notice 121094
The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs on 28/11/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 121091
Direction is cancelled from: 1500 hrs 28/11/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 121090
Direction is cancelled from: 1430 hrs 28/11/2024
Manager NEM Real Time Operations
Cancellation - Inter-regional transfer limit variation - to manage Power System Security in NSW region - 28/11/2024
Refer AEMO Electricity Market Notice 121142
Constraint set I-QN_1000 was invoked from 0955 hrs until 1230 hrs 28/11/2024.
This constraint set contains equations with the following interconnector on the LHS;
NSW1-QLD1
Manager NEM Real Time Operations
Inter-regional transfer limit variation - to manage Power System Security in NSW region - 28/11/2024
In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked the following constraint set I-QN_1000 from 0955 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
NSW1-QLD1
Manager NEM Real Time Operations
Planned outage of the Red Cliffs - Wemen - Kerang 220kV line in the VIC region on 30/11/2024.
The Red Cliffs - Wemen - Kerang 220kV line in the Victorian (VIC) region is planned to be out of service from 0400 hrs to 1430 hrs on 30/11/2024.
A credible contingency event during this planned outage may require:
- Load shedding in the Victorian outer grid; and/ or
- Market intervention, such as the issuing of directions.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations