125113MARKET SYSTEMS27/02/2025 11:01:35 AM

CHG0101364 - A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.

Change Number: CHG0101364

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Hub
Change Title: A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.
Change Start Date & Time: 02/03/2025 09:00:00
Change End Date & Time: 02/03/2025 17:00:00
Outage Start Date & Time: 02/03/2025 10:00:00
Outage End Date & Time: 02/03/2025 14:00:00
Environment: Production
Participant Impact and Requirements: The following impacts are expected during this maintenance:
- All access to the Electricity B2B Hub will be unavailable.
- All access to the Gas B2B Hub and all ebXML gateways (AEMOMIBB, AGNLGWY, LVI & VENCORP) will be unavailable. CATS and MDMT transactions for VIC/QLD will be delayed during the maintenance window.
- Users are not required to take any action due to this change, however will need to enact manual workarounds for the outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
     
125112NON-CONFORMANCE27/02/2025 08:55:25 AM

NON-CONFORMANCE Region NSW1 Thursday, 27 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 27 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 27/02/2025 08:45 to 27/02/2025 08:55
Amount: -7 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
125098NON-CONFORMANCE26/02/2025 12:40:25 PM

NON-CONFORMANCE Region NSW1 Wednesday, 26 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 26 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BERYLSF1
Duration: 26/02/2025 12:15 to 26/02/2025 12:40
Amount: 76 MW
Constraint: NC-N_BERYLSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
125083NON-CONFORMANCE25/02/2025 11:00:18 AM

NON-CONFORMANCE Region VIC1 Tuesday, 25 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Tuesday, 25 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MOKOSF1
Duration: 25/02/2025 09:50 to 25/02/2025 11:00
Amount: 32 MW
Constraint: NC-V_MOKOSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
125082NON-CONFORMANCE25/02/2025 10:20:17 AM

NON-CONFORMANCE Region QLD1 Tuesday, 25 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 25 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: STAN-4
Duration: 25/02/2025 09:30 to 25/02/2025 10:20
Amount: -18 MW
Constraint: NC-Q_STAN-4

Auto-generated on behalf of Manager NEM Real Time Operations
     
125066MARKET SYSTEMS24/02/2025 09:24:56 AM

Completed - CHG0100546 - Production eMDM February Maintenance Release

Change Number: CHG0100546

Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management
Change Title: Production eMDM February Maintenance Release

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
125026INTER-REGIONAL TRANSFER23/02/2025 03:44:24 AM

Inter-regional transfer limit variation - BassLink Harmonic Filter - TAS region - 23/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - BassLink Harmonic Filter - TAS region - 23/02/2025

At 0305 hrs 23/02/2025 there was an unplanned outage of BassLink Harmonic Filter.

The following constraint set(s) invoked at 0305 hrs 23/02/2025
T-BLGC_HF_43MVAR

This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
124986INTER-REGIONAL TRANSFER22/02/2025 08:11:27 AM

Inter-regional transfer limit variation - Collector Windfarm - Yass (3L) 330 kV line - NSW region - 22/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Collector Windfarm - Yass (3L) 330 kV line - NSW region - 22/02/2025

A planned outage of Collector Windfarm - Yass (3L) 330 kV line in the NSW region was scheduled from 0600 hrs 17/02/2025 to 1600 hrs 24/02/2025.

The outage has been completed and Collector Windfarm - Yass (3L) 330 kV line returned to service at 0746 hrs 22/02/2025

Constraint set(s) revoked: N-CTYS_3L_WG_CLOSE

Manager NEM Real Time Operations
     
124971NON-CONFORMANCE21/02/2025 12:10:28 PM

NON-CONFORMANCE Region VIC1 Friday, 21 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Friday, 21 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MCKAY1
Duration: 21/02/2025 12:00 to 21/02/2025 12:10
Amount: -54 MW
Constraint: NC-V_MCKAY1

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm