Filter by category
Filter by Date
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1830 hrs 12/12/2024 to 1900 hrs 12/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1401 MW.
Manager NEM Real Time Operations
[EventId:202412120145_confirmed] Prices for interval 12-Dec-2024 01:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0205 hrs on 12 December 2024
PRICES ARE NOW CONFIRMED for trading interval 12-Dec-2024 01:45.
In accordance with Market Notice 121741 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412120205_confirmed] Prices for interval 12-Dec-2024 02:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0205 hrs on 12 December 2024
PRICES ARE NOW CONFIRMED for trading interval 12-Dec-2024 02:05.
In accordance with Market Notice 121745 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412120200_confirmed] Prices for interval 12-Dec-2024 02:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0205 hrs on 12 December 2024
PRICES ARE NOW CONFIRMED for trading interval 12-Dec-2024 02:00.
In accordance with Market Notice 121744 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412120155_confirmed] Prices for interval 12-Dec-2024 01:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0205 hrs on 12 December 2024
PRICES ARE NOW CONFIRMED for trading interval 12-Dec-2024 01:55.
In accordance with Market Notice 121743 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412120150_confirmed] Prices for interval 12-Dec-2024 01:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0205 hrs on 12 December 2024
PRICES ARE NOW CONFIRMED for trading interval 12-Dec-2024 01:50.
In accordance with Market Notice 121742 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412120140_confirmed] Prices for interval 12-Dec-2024 01:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0205 hrs on 12 December 2024
PRICES ARE NOW CONFIRMED for trading interval 12-Dec-2024 01:40.
In accordance with Market Notice 121740 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Inter-Regional Transfer limit variation - Basslink
Inter-Regional Transfer limit variation - Basslink
There has been an unplanned outage of the Basslink interconnector.
The following constraint set was invoked at 0130 hrs 12/12/2024
I-BL_ZERO
The constraint set contains the following interconnector on the left hand side.
T-V-MNSP1
Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer to Market Notice 121721
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1600 hrs 11/12/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0830 hrs 12/12/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0930 hrs 12/12/2024 / further notice.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations