121760RESERVE NOTICE12/12/2024 09:04:31 AM

STPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 121734 has been updated at 0800 hrs 12/12/2024 to the following:

From 1500 hrs to 1930 hrs 16/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 733 MW at 1730 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121759RECALL GEN CAPACITY12/12/2024 09:09:42 AM

Request for Generator Recall Information for the period 16/12/2024 and 17/12/2024 for Region NSW

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 121760, 121762, and 121765.

Please provide Generator Recall Information for the period from 16/12/2024 to 17/12/2024, by 1200 hrs on 13/12/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf


AEMO Operations
     
121757RECALL GEN CAPACITY12/12/2024 09:07:27 AM

Request for Generator Recall Information for the period 16/12/2024 for Region VIC

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 121767.

Please provide Generator Recall Information for the period 16/12/2024, by 1200 hrs on 13/12/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf


AEMO Operations
     
121734RESERVE NOTICE12/12/2024 12:42:05 AM

STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

[1.] From 1530 hrs 16/12/2024 to 1600 hrs 16/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 10 MW at 1530 hrs.

[2.] From 1700 hrs 16/12/2024 to 1830 hrs 16/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 106 MW at 1730 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
121468CONSTRAINTS09/12/2024 09:04:22 AM

Update to system strength requirements in North Queensland

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 106175

AEMO and Powerlink are continuing to investigate system strength requirements in North Queensland.
Due to commissioning of Clarke Creek wind farm in Far North Queensland, the system normal equations have been revised.



A revision to the constraint equations will be implemented at 1100 hrs on Monday 9th December 2024.

The new combinations have now published in a limits advice document on AEMO's website. For more information refer to the new limits advice: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice

This advice contains all the combinations for Queensland for system normal cases. Additional information has been included in the limit advice to clarify the requirement to disconnect all inverters/turbines under certain system conditions.

The constraint equation in the Q-NIL set of the form below will be modified:

-Q_NIL_STRGTH_KBWF
-Q_NIL_STRGTH_MEWF

Two new equations have been added:

-Q_NIL_STRGTH_CKWF
-Q_NIL_STRGTH_CKWF_I

AEMO Operations
     
121295RESERVE NOTICE30/11/2024 04:40:16 PM

STPASA - Update of the suspect Lack Of Reserve Level 3 (LOR3) condition in the NSW Region on 06/12/2024

AEMO ELECTRICITY MARKET NOTICE

The suspect LOR3 condition advised in AEMO Electricity Market Notice No. 121292 has been reviewed.

AEMO considers this forecast LOR3 condition invalid. Subsequent STPASA runs are producing valid solutions.


AEMO Operations
     
121292RESERVE NOTICE30/11/2024 02:52:04 PM

STPASA - Suspect Lack Of Reserve Level 3 (LOR3) in the NSW Region on 06/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO considers that there is a suspect Forecast LOR3 condition for the NSW region for the following period:

From 1630 hrs 06/12/2024 to 1700 hrs 06/12/2024.

AEMO is currently investigating this LOR3 forecast condition to confirm whether they are valid.


AEMO Operations
     
121105RESERVE NOTICE27/11/2024 04:45:09 PM

Cancellation of Actual (LOR2) condition in the NSW region - 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR2) condition in the NSW region - 27/11/2024

The Actual LOR2 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121101 is cancelled at 1645 hrs 27/11/2024.

Manager NEM Real Time Operations
     
121101RESERVE NOTICE27/11/2024 03:48:50 PM

Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 27/11/2024

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1530 hrs.

The Actual LOR2 condition is forecast to exist until 1700 hrs.
The capacity reserve required is 685 MW
The minimum reserve available is 412 MW

AEMO is seeking an immediate market response.