Market Notices

121889RESERVE NOTICE14/12/2024 05:20:56 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121876 has been updated at 0510 hrs 14/12/2024 to the following:

From 1600 hrs to 2100 hrs 16/12/2024.
The forecast capacity reserve requirement is 1048 MW.
The minimum capacity reserve available is 517 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121888RESERVE NOTICE14/12/2024 05:19:30 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121839 has been updated at 0510 hrs 14/12/2024 to the following:

From 1600 hrs to 1830 hrs 17/12/2024.
The forecast capacity reserve requirement is 1058 MW.
The minimum capacity reserve available is 355 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121876RESERVE NOTICE13/12/2024 09:08:51 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region beginning on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period[s]:

[1.] From 1600 hrs 16/12/2024 to 2000 hrs 16/12/2024.
The forecast capacity reserve requirement is 1103 MW.
The minimum capacity reserve available is 710 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121873SETTLEMENTS RESIDUE13/12/2024 06:45:25 PM

[EventId:202412131845_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 13 December 2024 18:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1845 hrs on 13 December 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 December 2024.

Refer to market notice: 121856

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1845 hrs on 13 December 2024.

This is an AEMO autogenerated Market Notice.
     
121870NON-CONFORMANCE13/12/2024 04:55:23 PM

NON-CONFORMANCE Region QLD1 Friday, 13 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 13 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: KAREEYA1
Duration: 13/12/2024 16:50 to 13/12/2024 16:55
Amount: -21 MW
Constraint: NC-Q_KAREEYA1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121856SETTLEMENTS RESIDUE13/12/2024 03:25:46 PM

[EventId:202412131520_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 December 2024 15:20

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1520 hrs on 13 December 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 December 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1520 hrs on 13 December 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
121851SETTLEMENTS RESIDUE13/12/2024 03:00:23 PM

[EventId:202412131500_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 13 December 2024 15:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1500 hrs on 13 December 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 December 2024.

Refer to market notice: 121844

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1500 hrs on 13 December 2024.

This is an AEMO autogenerated Market Notice.
     
121844SETTLEMENTS RESIDUE13/12/2024 01:30:23 PM

[EventId:202412131330_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 December 2024 13:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 13 December 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 December 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1330 hrs on 13 December 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
121842GENERAL NOTICE13/12/2024 01:14:02 PM

CORRECTION: Update - Vulnerable lines in QLD region

AEMO ELECTRICITY MARKET NOTICE.

Update - Lightning vulnerable lines in QLD region

Refer to AEMO Electricity Market Notice 121840

Fix typo: Line 7141 should read Line 7143

At 2026 hrs 12/12/2024 the Kamerunga to Barron Gorge 132 kV Line 7184 and the Kamerunga to Barron Gorge 132 kV Line 7143 tripped.

The cause of the trip was identified as due to lightning.

In accordance with SO_OP_3715, AEMO now considers the Kamerunga to Barron Gorge 132 kV Line 7184 and the Kamerunga to Barron Gorge 132 kV Line 7143 to be vulnerable with a category of probable due to lightning.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm