Reclassification of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE
Duration: 11/12/2024 19:50 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Collinsville North - Proserpine No.7125 132 kV line and Collinsville North - Proserpine No.7126 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Collinsville North - Proserpine No.7125 132 kV and Collinsville North - Proserpine No.7126 132 kV
Duration: 11/12/2024 19:50 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Guybal Munjan - Chalumbin 857 275kV line line and Guybal Munjan - Chalumbin 858 275kV line line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Guybal Munjan - Chalumbin 857 275kV line and Guybal Munjan - Chalumbin 858 275kV line
Duration: 11/12/2024 17:08 until further notice
Constraint set(s) invoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121711 has been updated at 1500 hrs 11/12/2024 to the following:
1. From 1530 hrs 16/12/2024 to 1600 hrs 16/12/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 690 MW.
2. From 1630 hrs 16/12/2024 to 1930 hrs 16/12/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 292 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121693 is cancelled at 1400 hrs 11/12/2024.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121692 has been updated at 1400 hrs 11/12/2024 to the following:
1. From 1500 hrs to 1700 hrs 16/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
2. From 1900 hrs to 2030 hrs 16/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
1. From 1630 hrs to 1900 hrs 13/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1336 MW.
AEMO Operations
CHG0100201 | Planned maintenance affecting the AEMO Market Network ***Outage Updated***
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MarketNet
Change Title: Planned maintenance affecting the AEMO Market Network ***Outage Updated***
Change Start Date & Time: 16/12/2024 08:00:00 AEST
Change End Date & Time: 17/12/2024 17:00:00 AEST
Outage 1 Start Date & Time: 16/12/2024 08:12:00 AEST
Outage 1 End Date & Time: 16/12/2024 08:13:00 AEST
Outage 2 Start Date & Time: 16/12/2024 15:12:00 AEST
Outage 2 End Date & Time: 16/12/2024 15:13:00 AEST
Environment: Production
Participant Impact and Requirements: Planned maintenance will be conducted on the 16th of December 2024, between 08:00AM and 05:00PM AEST on the core network infrastructure within the AEMO Market Network in Brisbane.
During the change, there will be two instances of 1-3 second service disruption to MarketNet Services accessed via Brisbane as traffic moves from the active to the standby load balancing unit. All Services should return to normal after this time. Traffic via Sydney will not be affected during this time. AEMO recommends that all market participants with site to site VPN connections currently connected via Brisbane, to switch these connections to the Sydney site as a precaution.
Participants connecting via IPWAN and/or SSL VPN will be automatically connected to the Sydney site and do not need to take any action.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121709 has been updated at 1100 hrs 11/12/2024 to the following:
1. From 1700 hrs to 1900 hrs 16/12/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 391 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations