Market Notices

90102PRICES UNCHANGED01/09/2021 08:45:13 AM

[EventId:202109010825_confirmed] Prices for interval 01-Sep-2021 08:25 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0845 hrs on 1 September 2021

PRICES ARE NOW CONFIRMED for dispatch interval 01-Sep-2021 08:25.

In accordance with Market Notice 90097 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
90101PRICES SUBJECT TO REVIEW01/09/2021 08:40:16 AM

[EventId:202109010845_review] Prices for interval 01-Sep-2021 08:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0840 hrs on 1 September 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 01-Sep-2021 08:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
90100PRICES SUBJECT TO REVIEW01/09/2021 08:35:16 AM

[EventId:202109010840_review] Prices for interval 01-Sep-2021 08:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0835 hrs on 1 September 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 01-Sep-2021 08:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
90099PRICES SUBJECT TO REVIEW01/09/2021 08:30:22 AM

[EventId:202109010835_review] Prices for interval 01-Sep-2021 08:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0830 hrs on 1 September 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 01-Sep-2021 08:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
90098PRICES SUBJECT TO REVIEW01/09/2021 08:25:18 AM

[EventId:202109010830_review] Prices for interval 01-Sep-2021 08:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0825 hrs on 1 September 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 01-Sep-2021 08:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
90097PRICES SUBJECT TO REVIEW01/09/2021 08:20:16 AM

[EventId:202109010825_review] Prices for interval 01-Sep-2021 08:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0820 hrs on 1 September 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 01-Sep-2021 08:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
90096PRICES SUBJECT TO REVIEW01/09/2021 08:15:42 AM

[EventId:202109010820_review] Prices for interval 01-Sep-2021 08:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0815 hrs on 1 September 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 01-Sep-2021 08:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
90095RESERVE NOTICE01/09/2021 08:33:02 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 07/09/2021

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 90093 has been updated at 0800 hrs 01/09/2021 to the following:

From 1900 hrs 07/09/2021 to 2030 hrs 07/09/2021.
The forecast capacity reserve requirement is 250 MW.
The minimum capacity reserve available is 205 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
90094POWER SYSTEM EVENTS31/08/2021 06:00:03 PM

Update - Non-credible contingency event - NSW Region - 31/08/2021

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - NSW Region - 31/08/2021

Refer AEMO Electricity Market Notice 90077

At 1140 hrs the Eraring main 500 kV bus tripped.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

The Eraring main 500 kV bus was returned to service at 1745 hrs.

Manager NEM Real Time Operations