Market Notices

112248RECLASSIFY CONTINGENCY13/12/2023 01:44:23 PM

Update - Non-credible contingency event - TAS region - 13/12/2023

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 13/12/2023

Refer AEMO Electricity Market Notice 112247

The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.

Region: TAS

Elements: Hadspen - Palmerston No.3 & No.4 110 kV lines
Duration: 1335 hrs 13/12/2023 until further notice
Constraint set(s) invoked: T-HAPM_110_N-2

Manager NEM Real Time Operations
112247POWER SYSTEM EVENTS13/12/2023 01:43:17 PM

Non-credible contingency event - TAS region - 13/12/2023

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 13/12/2023

At 1324 hrs the Hadspen - Palmerston No.3 & No.4 110 kV lines tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
112246RECLASSIFY CONTINGENCY13/12/2023 01:35:30 PM

Reclassification of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV

Duration: 13/12/2023 13:35 until further notice

Constraint set(s) invoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1


Auto-generated on behalf of Manager NEM Real Time Operations
112245RECLASSIFY CONTINGENCY13/12/2023 01:24:35 PM

Cancellation of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown

Cancellation time: 13/12/2023 13:24

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 112219

Auto-generated on behalf of Manager NEM Real Time Operations
112244RECLASSIFY CONTINGENCY13/12/2023 01:19:35 PM

Cancellation of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV

Cancellation time: 13/12/2023 13:19

Constraint set(s) revoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1


Refer AEMO Electricity Market Notice 112217

Auto-generated on behalf of Manager NEM Real Time Operations
112243RESERVE NOTICE13/12/2023 01:03:11 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1700 hrs 14/12/2023 to 1830 hrs 14/12/2023.
The forecast capacity reserve requirement is 1286 MW.
The minimum capacity reserve available is 988 MW.


Manager NEM Real Time Operations
112242RESERVE NOTICE13/12/2023 12:58:47 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1930 hrs 14/12/2023 to 2000 hrs 14/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1323 MW.


Manager NEM Real Time Operations
112241RESERVE NOTICE13/12/2023 12:57:30 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1530 hrs 14/12/2023 to 1930 hrs 14/12/2023.
The forecast capacity reserve requirement is 1259 MW.
The minimum capacity reserve available is 344 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
112239GENERAL NOTICE13/12/2023 12:29:31 PM

Fast Frequency Response Market - Increase in R1 FCAS volume 18 December 2023.

AEMO ELECTRICITY MARKET NOTICE

Following review of the operation of the Very Fast FCAS market, from 1300 hrs AEST on Monday 18 December AEMO will:

Increase the cap on dispatch of Very Fast Raise (R1) Contingency FCAS from 175 MW to 225 MW

Retain the existing cap on dispatch of Very Fast Lower (L1) Contingency FCAS at 100 MW

No other changes to the dispatch of Very Fast FCAS or FCAS constraint equation changes will be made on this date

For information on the Fast Frequency Response (FFR) initiative please visit the website at: https://www.aemo.com.au/initiatives/major-programs/fast-frequency-response

Andrew Groom
AEMO Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm