115365RESERVE NOTICE29/02/2024 02:20:05 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 115358 has been updated at 1415 hrs to the following:

[1.] From 1600 hrs 29/02/2024 to 1830 hrs 29/02/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 957 MW.

Manager NEM Real Time Operations
115364MARKET INTERVENTION29/02/2024 04:46:21 PM

Direction - SA region 29/02/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 29/02/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1705 hrs on 29/02/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
115361MARKET INTERVENTION29/02/2024 02:11:33 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 115359

The synchronous generating units currently expected to be synchronised in SA from 0900 hrs 01/03/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1700 hrs 29/02/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
115359MARKET INTERVENTION29/02/2024 12:59:52 PM

Possible intervention to manage power system security in South Australia (SA) Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in South Australia (SA) Region

The synchronous generating units currently expected to be synchronised in SA from 0900 hrs 01/03/2024 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
115358RESERVE NOTICE29/02/2024 11:25:21 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 115347 has been updated at 1115 hrs to the following:

[1.] From 1530 hrs 29/02/2024 to 1900 hrs 29/02/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 846 MW.

Manager NEM Real Time Operations
115355MARKET INTERVENTION29/02/2024 08:19:27 AM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 28/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 28/02/2024

Refer Market Notice 115295

The AEMO Intervention Event and all associated directions are cancelled from 0815 hrs 29/02/2024

Manager NEM Real Time Operations
115347RESERVE NOTICE29/02/2024 12:51:06 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 115302 has been updated at 0050 hrs to the following:

[1.] From 1500 hrs 29/02/2024 to 1630 hrs 29/02/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 822 MW.

[2.] From 1800 hrs 29/02/2024 to 1900 hrs 29/02/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 852 MW.

Manager NEM Real Time Operations
115302RESERVE NOTICE28/02/2024 05:09:56 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 115291 has been updated at 1630 hrs to the following:

[1.] From 1530 hrs 29/02/2024 to 1600 hrs 29/02/2024.
The forecast capacity reserve requirement is 1360 MW.
The minimum capacity reserve available is 1158 MW.

[2.] From 1830 hrs 29/02/2024 to 1900 hrs 29/02/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1087 MW.


Manager NEM Real Time Operations
115295MARKET INTERVENTION28/02/2024 04:41:01 PM

Direction - SA region 28/02/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 28/02/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1635 hrs on 28/02/2024.

Intervention pricing does not apply to this AEMO intervention event.